Achieving effective implementation: an evaluation of a
collaborative land use planning process.
by Albert, Karin H.^Gunton, Thomas I.^Day, J.C.
The results of the KMT survey show that two criteria were ranked as
very important: providing clear objectives to guide implementing
agencies (mean 4.67), and strong commitment of implementing officials
(mean 4.58) (Table 2). One criterion was ranked as only somewhat
important: favorable socioeconomic conditions for land use plan
implementation (mean 3.0). Three criteria were ranked as not very
important: small target group as a percentage of the total population
affected by the land use plan (mean 1.63), minimal behavioral changes
required to comply with the land use plan (mean 2.21), and small
differences in values among stakeholders (mean 1.83). All other
variables were ranked as important (means 3.5 to 4.5). The KMT rankings,
therefore, are generally consistent with the implementation literature
with the following exceptions. Table members did not think that value
differences, size of the target group affected by implementation, and
magnitude of behavioural changes, were important conditions for
successful implementation.
The KMT was also asked to assess the degree to which these criteria
were met in the KLRMP on a five-point scale ranging from strongly agree
to strongly disagree. The results of this assessment help test the
relative importance of the criteria by identifying which of them are
correlated with a successful implementation process. The survey results
show that the respondents considered sixteen criteria as met (means
greater than 3.5) and nine criteria as only partially met (means between
2.5 and 3.5). No criterion that was considered important for
implementation success was considered as not met in the KLRMP
implementation process (Table 2). The two criteria not met in the case
of the KLRMP--having only a small target population affected by the land
use plan, and small differences in values among stakeholders--were
ranked as unimportant for implementation success by the survey
respondents.
Formal rankings in the KMT survey were complemented with responses
to open-ended questions. According to two table members (9%), one
important factor in ensuring implementation success, in the case of the
KLRMP, was the long history of cooperation between local government
agencies and different sectors in the region. Local government agencies
and the resource and environmental sectors worked together for many
years prior to the KLRMP to develop and implement local resource use
plans. Many of the same players involved in implementing these plans
also participated in the Kamloops land and resource management planning
process and later on the monitoring table. They brought with them a
spirit of trust and willingness to cooperate that helped overcome some
of the initial challenges of getting a diverse group of people to work
together. A further three respondents (13%) mentioned the importance of
developing trust between stakeholders. Four others (17%) pointed to the
strong commitment of local implementing agencies as a key factor in
furthering implementation. These open-ended responses in the survey are
also represented by criteria in Table 2 that were ranked as important or
very important.
In their answers, the table members also identified a number of
challenges and issues in plan implementation with the following
frequencies of occurrence:
* Clarification of intent of objectives (9%): The KLRM Plan does
not include statements of intent. Implementation depends, therefore, on
interpretation of objectives, which can create disputes over intent that
can undermine implementation. The KMT emphasized that developing
statements of intent for ambiguous objectives aids implementation by
helping to ensure that all parties have the same understanding of what
objectives mean.
* Continuity of membership (9%): Related to the challenge of
understanding intent is ensuring continuity of membership at the
monitoring table. Maintaining continuity in membership allows for
relationships to grow and ensures continuation of the cooperative
culture of the monitoring table that develops over time.
* Orientation and training for new table members (9%): The KMT
expressed concern that if new members are added, they must be oriented
to the overall planning process. Orientation should include a history of
the planning process, principles, values, ground rules, and
decision-making processes.
* Confirmation and consistency of government commitments (21%): The
monitoring table responses indicate that the linking of planning
strategies and objectives, and integration of commitments into agency
work plans, remain ongoing challenges. A number of KMT respondents are
uncertain with respect to the current provincial government's
commitment to KLRMP implementation. Clearly, government policy on this
issue needs to be clarified to avoid uncertainty, and potentially, loss
of commitment by stakeholders to plan implementation. Related to this
challenge is consistency and continuity of government policy and
direction. Governments need to honor the agreements reached by the KLRMP
Table. This includes continuing to provide funding for implementation of
key components of the plan. In the case of the KLRMP, the provincial
government has cut funding for several programs that were part of the
agreement package. Cutting essential program components can have a
detrimental impact on the commitment of the affected sector, or other
parties interested in implementation of the land use plan agreement.
* Ongoing information sharing between participants (9%):
Respondents emphasized that with so many different agencies involved in
implementation, cooperation and information sharing between agencies are
very important. Regular meetings of the KMT, the KIAMC, and other
working groups ensure cooperation and information exchange continue.
* Improvements to the monitoring framework and timetable (13%):
Respondents generally agreed that the monitoring framework has
appropriate indicators for monitoring each objective. But there is room
for improvement. Several respondents observed that linkages between
desired outcomes and agency program objectives need to be strengthened.
The monitoring table expressed some dissatisfaction with failure to meet
time lines in implementing the KLRMP. Given resource constraints,
implementation strategies need to be prioritized and a realistic
schedule drawn up.
Implications of Findings for Plan Implementation
Effective implementation is an infrequent event in resource
planning (Margerum 1999; Talen 1996). Therefore, the implementation of
the KLRMP provides a rare opportunity to evaluate a successful
implementation process. Assessments in Table 2 show that twenty-three
implementation criteria were ranked as important to very important by
stakeholders in achieving this success. This finding illustrates that
implementation of a land use plan is a complex undertaking that requires
attention to a broad range of issues to achieve implementation success.
These range from developing useful indicators and dealing with
scientific uncertainty to building respect and trust between individuals
from widely divergent backgrounds. The twenty-three criteria in Table 2,
therefore, provide a good checklist for assessing planning
implementation strategies. Responses in the open-ended sections of the
survey also highlighted aspects of these twenty-three criteria that
needed special attention in the implementation process. These include:
clarification of intent of objectives, continuity of membership,
orientation and training for new table members, confirmation and
consistency of government commitments, ongoing information sharing
between participants, and improvements to the monitoring framework and
timetable
Table 2 also illustrates that three criteria--small value
differences, small behavioral change, and small target population--were
not ranked as important by the stakeholders in the case study. However,
they are normally considered necessary conditions for successful
implementation. The fact that the KLRM Plan was successfully implemented
without meeting these three criteria provides evidence that they are not
always necessary for successful implementation. This finding on the
relative insignificance of these three criteria is contrary to the
implementation literature.
The ability to achieve successful implementation without meeting
these three criteria may be due to another key aspect of the KLRMP
process--collaboration in both development and implementation of the
plan. The strong link between collaboration and successful
implementation strongly supports the arguments on the benefits of CP.
The Kamloops Monitoring Table survey provides further documentation of
the key role played by CP, with 80% of respondents agreeing that CP was
important to very important in achieving implementation success.
Study Limitations
COPYRIGHT 2003 Wilfrid Laurier
University Reproduced with permission of the copyright holder. Further reproduction or distribution is prohibited without permission.
Copyright 2003, Gale Group. All rights
reserved. Gale Group is a Thomson Corporation Company.
NOTE: All illustrations and photos have been removed from this article.