A central technological feature of extractive industry is that
resource projects are lumpy and can be brought onstream at a time chosen
by an investor. Traditional project analysis has presumed that the
investor invests if the current net present value (NPV) of a project is
positive (Dixit and Pindyck 1994, pp. 4-5, 144-47). The theory of
investment under uncertainty shows that a positive NPV is necessary but
not sufficient for optimal immediate investment (optimal stopping); the
option of waiting to invest must also be evaluated.
Under certainty, the case examined herein, there is a similar
incentive to wait to invest in a lumpy project until the time at which
the project's value is maximized. Again, a positive NPV is
necessary but not sufficient for optimal immediate investment. We derive
an "r-percent" rule for optimal stopping that applies to the
rate of growth of the NPV of lumpy projects. At any time in an
extractive industry, for example, there are many known properties that
have not yet been developed. Some would produce a positive discounted
cash flow if opened immediately. The firm faces a choice of the time to
develop its property. At the optimal time, the time derivative of the
NPV of the project, as of any reference point in time, is zero. This
condition implies that at the optimal time of investment the current NPV
(in financial terminology the forward value) of the entire project is
rising at the force of interest. (1) Prior to that time the forward
value is rising at a rate that exceeds the force of interest, and
investment is optimally postponed. (2)
The idea of postponing the time to cut trees, to develop rural land
or public infrastructure, or to serve wine is not new. But the
applicability of postponement considerations to all lumpy investments
has not been stressed. Nor has there been explicit recognition that a
simple, intuitive, r-percent stopping rule applies generally. Marglin
(1963) seems to have been the first to argue that postponement should be
considered for any irreversible, lumpy investment. He cites Bain (1960)
as the first to raise the point in print. After two decades, Porter
(1982, 1984) revives the argument for a "new" way of
evaluating nonrenewable resource projects under certainty, taking the
option to postpone into account. He speculates that pessimism as to
future commodity prices may have been a factor in limiting attention to
now-or-never decisions in models of petroleum and minerals. (3) Neither
Marglin nor Porter, however, discerns an r-percent rule. Arnott and
Lewis (1979), Chiang (1984), Mishan (1988), Clarke and Reed (1990),
Brealey and Myers (2003), and Hands (2004) derive a timing rule similar
to the r-percent rule of the present article, but do not emphasize its
generality beyond selected land and natural resource investments. In
finance, postponement has gained importance only recently, as an outcome
of analysis under uncertainty. The solution is presented as a
calculation of certain critical values, namely, the optimal time of
investment or the value of the investment at that time (Dixit and
Pindyck 1994, pp. 138-49), or else as a rule for a "present-value
index" (Moore 2000) or modified NPV or internal rate of return
(Capozza and Li 2002), rather than as an r-percent rule.
In the literature on nonrenewable resources no one has expressed
the investment decision using the rate of change of the entire program
value. Rather, r-percent rules have been expressed as changes in the
value of a unit of reserves. Application of the r-percent
optimal-stopping rule orders equilibrium investments in a way that is
not necessarily in order of NPV nor even of physical quality. As a
result, the "least-cost-last" anomaly is resolved without
resort to stochastic explanations. Consistently with the rule's
applicability to whole projects, quality and rent are seen to be
characteristics of projects rather than individual units of reserves.
Hotelling's r-percent rule for units of reserves is recast as an
equilibrium pricing algorithm in light of the stopping rule.
In a section on sequential projects we discuss how literature on
setup costs and optimal extraction initiated by Hartwick, Kemp and Long
(1986) derives ostensibly different conditions for the timing of new
investment. We discuss how the findings of this literature relate to
ours and link the two back to the canonical problem of forestry.
Nonrenewable Resources
A nonrenewable resource project involves an irreversible, lumpy
capital expenditure on capacity and an extraction plan which specifies
outputs in future time periods, a shut-down time, and possibly other
choices (Cairns 2001). We assume that investment is instantaneous and
continuous in intensity. By a lumpy investment we mean a capital
expenditure that extinguishes the option to invest at a later date for
either economic or technical reasons. A profit-maximizing firm chooses
its time of investment, [t.sub.0] [greater than or equal to] 0, such
that the project's net present value, as of time t = 0, is
maximized.
For a given choice of [t.sub.0], let the optimal level of capacity
be represented by K([t.sub.0]) and its installed cost by I(K([t.sub.0]),
[t.sub.0]). In the equilibrium into which the project fits, let the
optimal closing time be represented by T([t.sub.0]), the optimized net
cash flow at any time t [member of] [[t.sub.0], T([t.sub.0])] by [phi]
(t, [t.sub.0], K([t.sub.0])), and the optimal closing expense by
X(T([t.sub.0]), K([t.sub.0])). In general, the force of interest may
vary through time and is written r(s). At the present date, t = 0, the
value of a property developed at time [t.sub.0] [greater than or equal
to] 0 is
(1) [MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII].
We call V([t.sub.0]) the discounted forward value of the mine and
assume that it is twice differentiable.
If [t.sup.*.sub.0] [member of](0, [infinity]) is the optimal choice
(an interior solution) of [t.sub.0] then V([t.sup.*.sub.0]) > 0,
V([t.sup.*.sub.0]) > V(0) and V([t.sup.sub.0]) = 0. Let W([t.sub.0])
= V([t.sub.0])exp[MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII] be
the value of the project at the time of opening, [t.sub.0]. This value,
which we call the forward value, is traditionally identified as the NPV
at [t.sub.0]. By direct differentiation,
(2) [MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII],
or
(3) W([t.sup.*.sub.0])/W([t.sup.*.sub.0]) = r([t.sup.*.sub.0]).
At the optimal investment time [t.sup.*.sub.0], the discounted (to
time t = 0) forward value is nonnegative and stationary, and the forward
value (current NPV at time t = [t.sub.0]) is nonnegative and growing at
exactly the force of interest. (4)
Condition (3), an "r-percent" rule, is a necessary
condition for a (local, interior) maximum of the value of the investment
opportunity. In any equilibrium of the sector, even a noncompetitive
one, condition (3) must hold, regardless of the characteristics of the
resource or the extraction technology.
Condition (3) applies to the present value of the entire project,
and not to the net price of individual units of the resource. Even
though it is an r-percent rule, then, it is not Hotelling's rule.
Rather, it is an optimal-stopping rule.
The second-order condition for a maximum stipulates that, in a
neighborhood of [t.sup.*.sub.0], [d.sup.2]V([t.sub.0])/[dt.sup.2.sub.0]
[less than or equal to] 0. Let that neighborhood be ([t.sub.1],
[t.sub.2]).Then V([t.sub.0]) [greater than or equal to] 0 when [t.sub.0]
[member of] ([t.sub.1], [t.sup.*.sub.0]). Therefore,
(4) [MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII],
or
(5) W([t.sub.0])/W([t.sub.0]) [greater than or equal] r([t.sub.0])
when [t.sub.0] [member of] ([t.sub.1], [t.sup.*.sub.0]).
At a time before the optimal time of investment, the forward value
of the investment, conditional on having to invest at that time, is
rising faster than at the force of interest. Similarly, just after the
optimal time, the forward value is rising more slowly than at the force
of interest:
(6) W([t.sub.0])/W([t.sub.0]) [less than or equal to] ([t.sub.0])
when [t.sub.0] [member of] ([t.sup.*.sub.0], [t.sub.2]).
The market value of the investment opportunity (presuming optimal
timing, i.e., striking at time [t.sup.*.sub.0]) at any time t <
[t.sup.*.sub.0] is
(7) [MATHEMATICAL EXPRESSION NOT REPRODUCIBLE IN ASCII].
(Recall that W(t) is the forward value of developing the project at
the time in question, t < [t.sup.*.sub.0].) By condition (7),
(8) [??](t) = r(t)[PI](t):
the market value of the whole project, not of individual units of
the resource, is rising at rate r(t). As in Hotelling's rule, the
total return on the investment opportunity is a capital gain from not
developing until the optimal time, [t.sup.*.sub.0]. That is to say,
under certainty, at any time t < [t.sup.*.sub.0], there is a value to
the option to wait, namely, [PI](t) - W(t) > 0. The time paths for
these various expressions of value are illustrated in figure 1.
[FIGURE 1 OMITTED]
The option of waiting to invest until time [t.sup.*.sub.0] provides
value similar to that demonstrated in the real-options literature. Even
a mineral deposit whose present value is negative if developed now (V(0)
< 0) has a positive market value if there exists a to such that
W([t.sub.0]) > 0. This positive value is often attributed entirely to
uncertainty, but in the present model it arises from optimal management
under certainty.
COPYRIGHT 2007 American Agricultural Economics
Association Reproduced with permission of the copyright holder. Further reproduction or distribution is prohibited without permission.
Copyright 2007, Gale Group. All rights
reserved. Gale Group is a Thomson Corporation Company.
NOTE: All illustrations and photos have been removed from this article.