The Institute for Local Self-Reliance (ILSR), Washington, D.C., in
cooperation with Penn State's Hamer Center for Community Design
(Hamer Center), University Park, Pa., has conducted a deconstruction
pilot project to determine cost-effective methods to remove lumber and
other materials from a Neighborhood Transformation Initiative abandoned
house. The U.S. Environmental Protection Agency (EPA) funded the project
and the city of Philadelphia provided the house for deconstruction.
Kevin Brooks Salvage (KBS), a Philadelphia contractor, performed
the deconstruction work on the 3224 Susquehanna unit, half of a
residential twin building. ILSR and the Hamer Center selected KBS to do
the work because the firm provided the lower bid and the more complete
bid package.
The project work took place from March 27 to April 7, 2006. At the
Hamer Center's direction, the KBS crew experimented with the use of
a mechanized, panelized approach of removing lumber. The dismantling
process involved cutting the roof and floor panels into sections and
removing them to an off-site location for processing. The project
diverted bricks, lumber, metal and architectural features from disposal.
GETTING STARTED
Brad Guy, Hamer Center associate researcher, prepared the
project's request for qualifications (RFQ) using language and
concepts from several model green building documents.
The RFQ stated up front the project's overall purpose of
deconstructing and recovering building materials from one or more row
houses condemned by the city of Philadelphia.
The project's specific focus was exploring innovative
techniques for dismantling urban row houses to reclaim the maximum
amount of roof and floor structural materials in the most cost-effective
manner for reuse and recycling.
The RFQ outlined:
* Services to be required
* Submittal requirements
* Additional considerations for evaluation
* Schedule.
As basis for award, the RFQ stated that the contract would be
awarded to the contractor offering the most favorable terms, and with
the following factors being considered:
* Price
* Qualifications and capabilities
* Proposed techniques to recover materials
* Waste management strategy
* Disposition of recovered materials
* Personnel
* Schedule.
In January 2005, ILSR distributed the RFQ to 17 prospective salvage
and deconstruction companies identified by the Hamer Center, as well as
to the Board of Directors of the Delaware Valley Green Building Council.
As a result of the outreach effort, ILSR received two submissions by the
March 11, 2005 deadline. ILSR and the Hamer Center carefully reviewed
the materials and determined that both firms were qualified and would be
invited to submit a bid proposal for the designated buildings.
The Hamer Center chose Kevin Brooks Salvage (KBS), a
Philadelphia-based firm, as the deconstruction contractor because the
company submitted the lower bid and the more complete bid package.
KBS's total bid amount for deconstructing both properties fell
within the project budget and ILSR officially requested permission from
the city to deconstruct the two Susquehanna houses.
GETTING RESULTS
The project diverted bricks, lumber, metal and architectural
features from disposal. Most of the bricks were used for onsite
backfill, and additional recovered materials included:
* Eight hundred and forty linear feet of hemlock joists were sold
to a broker for remilling ($1,680).
* Finished pine floor was sold ($500).
* Five hundred linear feet of recovered lumber were provided to a
local source ($250).
* Two tons of metal (radiators, oil tank, duct work, gas lines,
plumbing lines) were sold to local scrap dealers ($600).
* Architectural features have been marketed through KBS's
architectural salvage business, Found Matter. Two decorative tin pieces
and one wrought iron gate have been sold to date ($500).
* Kevin Brooks decided to keep the turret ($3,000 value) for his
own use.
* In addition, $800 worth of brown stone and two $200 worth of
decorative tin pieces are still for sale at Found Matter.
To summarize, the total value of the recovered materials is $7,530,
and, as of December 2006, $6,530 of materials have been sold or directly
used by KBS. The remaining $1,000 worth of materials is for sale in the
Found Matter store.
At this point in time, there is very little, if any, deconstruction
occurring in the removal of abandoned housing in Philadelphia.
Mechanized demolition is the process for removing larger numbers of
buildings at one time, and deconstruction is much more labor-intensive
and costly than this form of building takedown. However, in
Philadelphia, there are many units of housing attached to other
structures in a row or twin, and these houses are often removed using a
combination of mechanized and hand demolition, a more labor intensive
process that safeguards the structural integrity of the adjoining house
or houses.
Table 1 (left) compares the current Susquehanna cost data with
average costs for both hand and mechanized demolition. All labor costs
are based on current prevailing wage. The Susquehanna project data
demonstrate that deconstruction can be cost-competitive with hand
demolition when there are sufficient recoverable materials with market
value to offset higher labor costs. The $8.94 net cost per square foot
for the Susquehanna project falls within the range of the average hand
demolition cost ($7.75-$9.30).
ILSR and Kevin Brooks Salvage, the Susquehanna Project contractor,
believe that the costs could be even lower in future projects based on
the following factors:
* On-time dumpster placement, removal, and replacement procedures
as delays in placing and removing full dumpsters resulted in additional
labor costs because workers had to handle some waste materials more than
once.
* Better onsite efficiency using improved removal practices based
on lessons learned from the pilot. For example, the panelization work
was a first-time effort for the crew and likely would require less time
with more experience.
* Improving the economy of scale by removing more than one house at
a time.
The original goal was the deconstruction of two adjoining housing
units that would have resulted in a lower cost per unit than from
removal of a single unit.
Also, the final 3224 Susquehanna data may show a lower net cost if
additional recovered materials are sold.
CONCLUSIONS
The project's supporters see many successes in the Susquehanna
Deconstruction project.
First, the pilot project demonstrated a cost-effective approach in
removing lumber and other recoverable materials from abandoned houses.
Current market development efforts will likely create more incentives
for contractors to recover the materials. For example, architects can
gain LEED credits (the U.S. Green Building Council's (USGBC)
Leadership in Energy and Environmental Design green building
certification program) for use of recovered materials. Habitat for
Humanity Philadelphia has been working with ILSR in exploring the
possibility of using reclaimed building materials in the Stiles Project,
the city's first LEED-certified affordable housing.
In addition, it introduced panelization as a viable consideration
for deconstruction contractors. While Kevin Brooks admits that the
panelization process was more costly than using his regular disassembly
methodology, he attributes some of the added expense to his inexperience
in using the new approach. He is open to using panelization in future
work, especially for commercial and industrial buildings where there are
no adjacent properties that can be damaged. He believes the technique is
"cleaner," can require less onsite time, and allows for the
disassembly of materials at an offsite location.
The project also supported the development of the emerging
restoration industry in Southeastern Pennsylvania by increasing
awareness of deconstruction and architectural salvage among the green
building community, local architects, city officials, and the general
public.
This growing awareness is contributing to the non-profit
organization, Second Chance, in its current efforts to open a major
reuse retail yard in Philadelphia within the year.
The new retail yard is expected to greatly increase the demand for
used building materials in the region.
And finally, it assisted KBS in obtaining additional deconstruction
and architectural work and publicity. The Philadelphia Inquirer article
about the project helped Kevin Brooks secure two additional jobs,
provided more work leads, and resulted in publicity in a Philadelphia
weekly newspaper. One of the projects is the interior deconstruction of
70,000 square feet of warehouse space and the full deconstruction of two
warehouse structures in Phoenixville, Pa. In the second project, KBS
removed dimensional lumber and the truss system from an 1850s structure
in the Germantown section of Philadelphia. Three thousand board feet of
hemlock were recovered and sold for reuse in a restaurant renovation
project.
A secondary benefit of the project is the fact that owners stepped
forward and reclaimed three of the buildings that were designated for
demolition: 3947 and 3949 Aspen Street, and 3222 Susquehanna Avenue. It
is always preferable to reclaim rather than deconstruct buildings.
Finally, ILSR acknowledges that the project success is due to the
teamwork of all the participating partners, and trusts that ongoing
partnerships will build on the project momentum and continue to support
the emerging restoration economy in Southeastern Pennsylvania.
COPYRIGHT 2007 G.I.E. Media,
Inc. Reproduced with permission of the copyright holder. Further reproduction or distribution is prohibited without permission.
Copyright 2007, Gale Group. All rights
reserved. Gale Group is a Thomson Corporation Company.
NOTE: All illustrations and photos have been removed from this article.