Alenia ramps up on 787: Alenia Aeronautica is building
all-composite one-piece barrel fuselage sections for the 787 at a
brand-new facility in the south of Italy.
by MacRae, Duncan
The timing could not have been better. Only days after Boeing
Commercial Airplanes CEO Scott Carson and 787 programme leader Mike Bait
formally announced a delay of several weeks in the first flight of
Boeing's new long-range twin--thereby swinging the spotlight onto
production issues--Italian partner Alenia Aeronautica invited
representatives of the global media to visit its brand-new facility
dedicated to the production of all-composite one-piece barrel (OPB)
fuselage sections for the aircraft. The new plant is located at
Grottaglie, near Taranto, in the Puglia region in southern Italy.
[ILLUSTRATIONS OMITTED]
For Alenia, it was an opportunity to showcase its cutting-edge
capabilities in composite aerostructures. Parent company Finmeccanica is
making no bones about its ambitions in this area--it wants to leverage
its strategic involvement in the 787 into a strengthened role as an
indpendent prime partner in aerostructures. Finmeccanica is investing
heavily in the 787, having already ploughed 550 million [euro] into the
programme at various facilities across Italy--250 million [euro] in the
Puglia region (210 million [euro] at Grottaglie and 40 million [euro] at
Foggia), 40 million [euro] in the Naples area (Pomigliano d'Arco,
Nola and Casoria), plus 260 million [euro] for engineering activities.
Risk-sharing stake
The company expects that figure to double over the next couple of
years. But the gamble could pay off handsomely--Finmeccanica's 14%
risk-sharing stake in the 787 airframe is expected to turn into
high-margin business once the programme ramps up to cruising speed.
Analysts are predicting that the 787 could be contributing the
equivalent of half the company's 2006 EBIT by the turn of the
decade. Significantly, financial analysts were invited to tour the
Grottaglie plant several months before the media.
Whether by accident or design, Alenia is making its move at a time
when the European aerostructures sector is in upheaval in the wake of
Airbus plans to sell off some production facilities and outsource a
greater share of future programmes under its Power 8 cost-cutting
programme. Alenia is not actually bidding to take over any of the Airbus
facilities currently on the block, though it will be seeking to
participate in the A350XWB programme, as it has done on previous Airbus
programmes.
For Boeing, the Grottaglie visit provided an opportunity to
reassure observers that the "high-tech, high-risk" portion of
the programme--production of OPB fuselage sections in carbon fibre
composite, which has never been attempted on this scale--is proceeding
smoothly. The problems that have occurred (e.g. the much ballyhooed
shortage of fasteners) are decidedly low-tech and, by implication, more
readily resolved. The 787 global supply chain may not yet be running as
smoothly as planned (see box) but the problems do not seem
insurmountable.
Maurizio Rosini, who is COO of Alenia Composite, the subsidiary
that runs the Gottaglie operation, says that the fastener problem is
gradually improving and that in any case it raises no real concerns--the
use of slightly under-sized temporary fasteners facilitates the removal
and replacement process by ensuring that holes do not have to be
re-drilled. The other issue--installation of tubing and wiring before
sections are shipped from Grottaglie, something that is not being done
today--is expected to be resolved "within months".
The Grottaglie plant has been built on a site formerly used by
Alitalia for maintenance of its MD-80 fleet. The site was extended to
build the new 65,000[m.sup.2] fuselage barrel facility, and there is
still plenty of room for further expansion, if needed. Construction
started in 2005, and production got under way in November 2006. The
runway at the adjacent Marcello Arlotta airport was also strengthened
and extended (from 1,700m to 3,500m). Funding for the latter work (130
million [euro]) was provided by the Puglia region under its Regional
Transport Plan.
[ILLUSTRATION OMITTED]
Alenia Aeronautica's workshare on the 787 includes sections 44
(above the wing) and 46 (immediately aft of the wing), as well as the
horizontal stabliliser, produced at the company's historical centre
of excellence for composites at Foggia, about 200km away.
The production flow starts in the clean room (at 175,000[m.sup.3]
claimed to be the largest in Europe), where layers of prepreg tape are
applied onto a huge invar mandrel almost six metres in diameter. The
mandrel matches the shape and dimensions of the finished barrel
sections--8.5m in length for section 44, 10-15m (depending on the 787
version) for section 46, with a diameter of 5.74m. The mandrel is
rotated while the Ingersoll tape layer applies the fibre. The plant
currently has two tape layers in operation, with a third in the process
of installation.
This process is not entirely automated. David Brigante, Alenia
Aeronautica Senior VP Commercial and Credit Management, explains that
the first layer, applied once the stringers have been positioned on the
mandrel, is placed manually, as is the final layer, which includes the
metallic mesh necessary to ensure electrical continuity of the airframe.
The completed barrel section is then bagged and cured, along with its
integral stringers, in an 8.5m-diameter autoclave.
After debagging, the section (with the mandrel still in place) is
transferred to a trimming and drilling station where apertures are cut
out for doors and windows. The collapsible mandrel is then removed and
replaced by two large support rings, one at each end of the section,
which carry the section for the remainder of the work sequence.
Subsequent operations include 100% non-destructive inspection to check
for defects in the composite structure; drilling and attachment of the
frames (supplied by Alenia's Pomigliano factory); completion and
inspection; and installation of the floor structure. With the floor
structure in place, the barrel sectios are sufficiently rigid for the
support rings to be removed, prior to systems installation and
preparation for shipment.
Completed shipsets are rolled out of the factory and directly
loaded onto the Dreamlifter for shipment to South Carolina. They are
delivered to Global Aeronautica, a joint venture between the Italian
firm and Vought. The joint venture assembles the sections from
Grottaglie, the adjoining forward fuselage section (section 43, made by
Kawasaki Heavy Industries), plus section 11/45 (the centre landing gear
bay and centre wing box, made by KHI and Fuji Heavy Industries and
joined by FHI). Vought builds and assembles the aft portion of the
fuselage (sections 47 and 48) at an adjoining facility. The completed
aft fuselage assembly is transferred to Global Aeronautica for shipment.
The forward fuselage and nose section are built by Spirit
Aerosystems.
Production rates
Rosini is cagey about production rates, refusing to confirm or deny
one analyst's assertion that 10 shipsets per month was the
near-term target. He simply asserts that Grottaglie will be capable of
meeting Boeing's requirements, i.e. 112 aircraft by the end of
2009. One thing is clear--production is gaining momentum, under the
watchful eye of the 20-or-so Boeing engineers still present on the site.
It took almost six months to deliver the first five shipsets, whereas
the interval between the fifth and sixth shipsets was down to less than
two weeks. As the learning curve kicks in and the third tape layer comes
on line, this can only accelerate.
In the meantime, Rosini claims the facility is already achieving
"zero defect" levels of quality.
RELATED ARTICLE: Fixing the fastener problem.
What to make of production problems on the 787 programme? With
Boeing under pressure to ramp up rapidly in response to soaring customer
demand, the 6-10 week slippage in the first flight date marks a setback.
Officially, the company still hopes to meet its May 2008 first-delivery
milestone, but 787 programme leader Mike Bair acknowledges the fact that
the compressed flight test schedule is now "very tight". Bair
says the schedule slippage on aircraft No. 1 is due to a variety of
factors. First, following an unexpected shortage of fasteners, thousands
of temporary fasteners were used to assemble the aircraft rolled out on
8 July, oil of which must now be replaced. Another contributor is the
amount of "travel work" being done in Everett--systems
installation and wiring work that is supposed to be performed by
external suppliers. Blair also said there had been problems due to
assemblies arriving at Everett with documentation which did not match
the actual work still to be done; documentation discrepancies had to be
resolved manually. Finally, Honeywell's work on coding and
integration of flight control system software is taking longer than
expected. The bottom line is that the 787's highly sophisticated
globe-spanning production network has been knocked off the rails by a
combination of travel work issues and the need to revert to temporary
fasteners. Should the system have done better? Bair says that the
production system was not conceived to cope with the level of travel
work that has occurred. The fastener problems basically "jumbled
up" the way the first aircraft was put together, he argues. He
insists the overall production system will be robust "when the
system is working the way it's supposed to". The size of the
window for the first flight date suggests the situation is not yet
completely under control.
COPYRIGHT 2007 Aerospace Media
Publishing Reproduced with permission of the copyright holder. Further reproduction or distribution is prohibited without permission.
Copyright 2007, Gale Group. All rights
reserved. Gale Group is a Thomson Corporation Company.
NOTE: All illustrations and photos have been removed from this article.