INTRODUCTION
HANGING A DOOR DEPENDS ON THE PROPER INSTALLATION OF THE DOOR
FRAME. Door frames consist of three primary parts: the strike jamb, the
hinge jamb, and the header. The strike jamb has the strike and deadbolt
preparation formed into it. The hinge jamb is prepared to accept the
hinges, and the header is formed to fit to the jambs. The door stop is
formed into the jamb at the factory and, if weather stripping is to be
installed, a pocket, called a kerf, can be formed into the jamb to
accept the weather stripping. The metal frames are then shipped, ready
for installation and few, if any, modifications are made on the job
site.
[ILLUSTRATION OMITTED]
Building codes require fire door assemblies in commercial buildings
such as offices, industrial facilities, hospitals, and schools, and a
steel frame with a fire door is a good way to meet these requirements.
Fire-rated openings are made up of a frame, door and hardware. Frames
are usually rated from 20 minutes to 3 hours with the fire rating the
total opening determined by the lowest rated component. For example,
using a 20-minute-rated door with a 90-minute-rated frame and hardware
results in a rating of 20 minutes. The fire rating is embossed on the
hinge jamb.
Metal frames come in a variety of designs. Most are made in an
unequal rabbet style with the frame being formed so that either a 1 3/4
or 1 3/8 door can be prepped into the frame. They also are available in
equal rabbet frames so that two doors of the same size can be hung into
the frame. Equal rabbet frames are usually used between two hotel rooms.
They can also be made in single rabbet frames, which are generally used
when the designer wants a no stop look.
History of Steel Frames:
Over the last 100 years there have been a lot of changes in steel
frames. They started as flat metal welded into the wall with stops
welded onto them. Most of the time the hinges were surface applied to
the frame.
Press-broke hollow metal frames were the next type of steel frame
to be developed. At the end of World War II contractors started using
drywall. Using slip in anchors, hollow metal frames where adapted to
this new type of wall
With the advent of drywall construction a new type of steel frame
was developed--"Prefinished Steel Door Frames." These frames
were designed to be installed over the drywall at the end of the
project.
HOLLOW METAL FRAMES
Hollow Metal or HM frames are usually made from 16-gauge steel,
with 14- and 18-gauge available. If the frame is assembled by the
distributor, it is referred to as a welded door frame. Welded frames are
delivered to the jobsite for installation during wall construction
without the doors. If the frame is assembled at the job site or
installed during wall construction, it is referred to as a knockdown
door frame or KD frame. One type drywall HM frame can be installed after
the sheetrock is in place using compression anchors. Hollow metal frames
are field painted.
PREFINISHED STEEL DOOR FRAMES
Prefinished frames are usually made from 20-gauge steel with
18-gauge available. The frame is cleaned, primed and painted with a
finish coat by the manufacturer and assembled at the job site.
ADVANTAGES OF PREFINISHED STEEL DOOR FRAMES
Prefinished frames are not Hollow Metal Frames. Installing a
prefinished frame during the finish phase of the project reduces the
possibility of damage to the door unit. Frames, doors and hardware can
be shipped to the project later, allowing more time to coordinate each
item so fewer mistakes are made in preparations. Prefinished steel door
frames come in both standard and adjustable profiles and are available
with a kerf, for the installation of weather stripping. Prefinished
steel door frames are available with any size sidelite, transom or
borrowed lite unit. They are designed to be installed after a wall is
built and all painting and other wall finishes are completed. Masking
around the door frames is not necessary because both the frame and wall
are finished. When using vinyl wall coverings, the covering is cut to
the rough opening and the frame is sleeved over the wall covering. No
calking is required around the frame. Prefinished frames can be
installed over floor coverings, eliminating the need to cut the flooring
to fit around the frame. Doors and finish hardware are installed at the
same time as the prefinished steel frame, rather than in separate stages
like hollow metal frames. Doors can be pre-hung using an adjustable
frame or hung while installing the frame. The door is used like a square
frame template to help check the frame for plumb, square and twist.
CASINGS
Casings are used to conceal the screws that are used to install
prefinished steel frames. There are three types of casings available
from the manufacturer: Standard Steel, Colonial Steel, and Aluminum.
Factory casings are snapped on to tabs on the frame. Wood trim can also
be installed over prefinished steel door frames instead of the factory
casings. To use wood trim, the prefinished steel door frame is ordered
without tabs and casings to provide a flat surface for the trim. Fire
ratings of prefinished frames are not affected by the use of different
casings. For example a 90-minute-rated frame can use jobsite wood trim.
[ILLUSTRATION OMITTED]
[ILLUSTRATION OMITTED]
[ILLUSTRATION OMITTED]
When a prefinished frame is installed at the end of the project,
there are a number of ways that savings are obtained. The largest
savings is achieved by not having to field paint the frames. Field
painting of frames costs at least $65.00 per opening. Because the
installation of the frame, door and hardware is done at the end of the
project, a number of man hours are saved. All the contractor has to do
is leave the correct sized rough opening and all sheetrock work,
plumbing, electrical, painting and wall coverings are completed before
the prefinished frames, finished doors and finish hardware are
installed. Time savings are obtained by not having to get hollow metal
frames to the job during wall construction. Painting of the wall is
completed without masking around the frames. Sheetrock is cut to the
rough opening not pushed behind the frame. Wall coverings are completed
before frame installation, not cut around the frame, so calking around
the frame is not required. This adds up to around $120.00 per installed
opening savings over hollow metal frames.
Preparation for Installation of Prefinished Steel Frames
Prefinished steel frames are shipped ready to install and
modifications should not be attempted in the field. Both the components
and the boxes in which they are shipped are marked to help with assembly
and installation instructions are placed in each header box by the
manufacturer.
[ILLUSTRATION OMITTED]
A few necessary steps must be completed before starting the
installation of prefinished steel door frames. First verify that all of
the door opening components, frame, doors, hardware, and hardware
reinforcements are on hand. The parts must be located and placed by the
opening. Because the frame, door and hardware are all installed at the
same time, any problems will be discovered while installing the first
door, rather than after several frames have been installed.
The rough openings for Prefinished Steel Door frames are different
than other types of frames. For single and paired door frames, it is 1
1/4" in width over door size and 1" in height from finish
floor over door height. For side lite frames it is 1 1/4" plus
door, plus glass size and 2" for each mullion in width and 1"
in height. For borrowed lite windows it is 1 1/4" plus glass and
mullions in width and height.
Measure the wall to make sure the frames are the correct size. The
width of the frame should be exactly the same as the finished wall
thickness or up to 1/8" wider. If the frame is smaller than the
wall, installing it over the wall will cause the frame to spread. This
will change the shape of the frame, affecting the swing of the door and
preventing it from closing properly. For example if the wall is designed
to be 4 7/8" you should order a 4 7/8" or 5" frame.
Frame components should be secured with drywall screws. Finish
screws are used to install the frame only when job site wood trim is to
be used.
Reinforcements for hardware are required for prefinished steel door
frames. They are metal formed to fit into the backside of the
prefinished steel door frame and are used behind parallel arm door
closers, rim exit devices, overhead door holders, and any other type of
hardware that will attach to the frame. Check with the manufacturer to
see where reinforcements are required and install them as needed. If
they were not provided with the prefinished steel door frame, they must
be obtained before the frames are installed. If hardware reinforcements
are not installed before beginning installation of the frame, the screws
holding the finish hardware will come loose and damage the frame. If it
is a fire rated frame and the reinforcements are not used, the fire
rating of the frame is voided.
[ILLUSTRATION OMITTED]
Prefinished steel door frame components are a finished product and
must be handled carefully to avoid scratching the paint or denting the
frame. They must be installed at the finishing stage of the job to
prevent damage from moving materials.
Installation of Standard Prefinished Door Frames
[ILLUSTRATION OMITTED]
TOOLS REQUIRED
* Screws
** Finished screws are used when job site wood trim is used
** Standard drywall screws are used on most installations.
* Level
** 2' and 6' magnetic
* Screw gun, usually cordless
COPYRIGHT 2007 Door and Hardware
Institute Reproduced with permission of the copyright holder. Further reproduction or distribution is prohibited without permission.
Copyright 2007, Gale Group. All rights
reserved. Gale Group is a Thomson Corporation Company.
NOTE: All illustrations and photos have been removed from this article.