Evaluation of the impact of reclamation regulations
and guidelines on ecological rehabilitation practices at the Estevan
surface coal mines (1996-1999), Saskatchewan.
by Aryee, Abednego
Luscar Ltd. is required by law to submit a pre-mining and
reclamation plan and a proposal for an assurance fund to SE to ensure
the decommissioning and reclamation of mining sites. Commenting on the
mine plan, an official of SE observed that Luscar Ltd. sets out its
reclamation plan in March of every year. Draft plans for mining and
restoration and the assurance fund which have been submitted by the
management of Luscar Ltd. since 1996, have met standards stipulated in
the 1996 regulations and have consequently been approved by the Minister
of Environment, Saskatchewan. An interview with SE regulators revealed
that the mining company has not defaulted in observing the requirements
of the assurance fund. The fund provides security against breach of the
permit conditions and rehabilitation requirements.
In order to monitor rehabilitation success, the mining company is
required to conduct field evaluations and submit semi-annual reclamation
reports to SE. The mining company submitted eight reclamation reports
between 1996 and 1999. The reports, supported by air photos, maps and
soil and plant surveys, illustrate hectares for which various
reclamation steps were undertaken, timing of all reclamation activities,
soil amendments applied and the results of seeding. These reports have
been reviewed and endorsed by SE officials.
Site-specific Restoration Programs
The issue of environmentally responsible mining in the Estevan area
is not whether the mine site will be restored, but the manner in which
restoration is accomplished. Luscar Ltd. is required to take measures in
dealing with and lessening the environmental impacts of coal mining
operations. An interview with officials of Luscar Ltd. revealed that
coversoil removal is normally conducted annually, during the unfrozen
conditions (summer), and takes place approximately six months ahead of
mining.
Currently, coal is mined by a 1,570W Bucyrus-Erie dragline, the
Prairie Queen, and 'Big Lou', a giant dragline (MacBean 2001:
4) in a series of parallel cuts--30 m wide strips up to 3.5 km in
length. Following coal removal, these pits are subsequently backfilled
and reclaimed in a regular manner: reclamation is done simultaneously
with mining operation. Overburden excavated from the active cut is used
to backfill the pit which is subsequently levelled. In line with the
rehabilitation plan, part of the spoil piles of mining has been levelled
to the required slope. Soil surveys undertaken by the mining company at
the Bienfait, Boundary Dam and Utility Mines indicate that topsoil
(A-horizon) materials with depths averaging 10-15 cm are found over the
pre-mined lands. The stockpiled soil is then spread on the levelled area
and seeded. A selective overburden handling technique' has been
incorporated into rehabilitation work at Bienfait, Utility and Boundary
Dam mines. According to mine officials, the technique selectively places
overburden materials with higher reclamation suitability into the upper
portion of the backfill of the mined lands (Luscar Ltd. 1996-2000).
Overburden materials (B-horizon) that are not suitable for plant growth
are buried deep in the backfilled area.
Site levelling and grading operations are undertaken by bulldozers,
scrapers and graders, with the objective of creating 10% slope and a
landscape acceptable to the proposed soft land uses: typically
agriculture (cropping), wildlife and recreation. Initial box cut and
final mine cuts normally retain greater slopes (10 to 20%). An
environmental planner of Luscar Ltd. indicated that after coversoiling,
the disturbed lands receive another lift in volume, which adds up to
approximately 15 cm in thickness after grading and compensates for the
metre of coal seam removed. According to the Guidelines, grading of land
should occur within two years of the initial disturbance (Luscar Ltd.
1996). Yet, soil replacement on parts of the mine sites of Bienfait,
Boundary Dam and Utility mines occurred within three years of initial
disturbance. In cases where cover soil was not available at a particular
site, engineers resorted to using other alternatives such as
transferring cover soil from other sites (Estevan Coal Corporation 1996)
instead of using suitable substrates such as residual hay, straw or wood
chip. Unless such 'supplier sites' have enough top-soil to
offset the deficiency, this practice can have adverse long-term
consequences such as nutrient depletion and low vegetative growth.
Revegetation of graded land for agriculture, rangeland and wildlife
is a significant part of ecological rehabilitation practices in the
Estevan area. Emphasis has been placed on quickly establishing
vegetation to control erosion and to achieve a self-sustaining plant
cover. Officials of Luscar Ltd. work in close collaboration with
personnel of SaskPower's Shand Greenhouse who currently conduct
revegetation in the Estevan area (SaskPower is the final custodian of
most of the rehabilitated lands in Estevan and owns the coalfields,
which are leased to the mining companies for mining operations). In
1999, germination trials were conducted at the greenhouse on five rare
native species for Luscar Ltd., including purple coneflower (Echinacea),
bird's foot trefoil (Lotus corniculatus), milkwort (Polygala
verticillata), salt bush (Baccharis halimifolia) and whorled milkweed
(Asclepias syriaca). These species have been used in seeding programs in
the Estevan area with 50% survival rates (Luscar Ltd. 2000).
In addition, measures were undertaken to prevent the transfer of
contaminated water into the underground water systems and Souris
River--the main river that drains the area. The SE-approved dewatering
procedure was followed. There was no water discharge from surface
impoundment and settling ponds at the Boundary Dam Mine between 1996 and
1997. However, between 1998 and 1999, a total of 899,208 m3 of water was
pumped from dewatering wells and settling ponds to approved discharge
points. Some of the water was discharged into SaskPower's Shand
Cooling Tower in 1999 (Luscar Ltd. 1999). Since this is a closed system,
there was no water quality analysis. Quality analysis was, however,
conducted on the remaining two-thirds of water discharged during the
period. Water samples were collected once a week and analyzed for
turbidity and suspended solids (TSS). The average TSS was 28.5 mg/l
which was below the legally allowed maximum level of 50mg/l (Table 1).
The average TSS for water tested at the Bienfait mine (total of
368,340.6 m3) between 1996 and 1999 was 19.8 mg/l which was below the
legally allowed maximum limit of 50 mg/l set by the SE guidelines
(Luscar Ltd. 1999). There was no water discharge from settling ponds in
1996, 1997, 1998 and 1999 (Luscar Ltd. 1996, 1999) at the Utility Mine
because settling ponds and wells were not in use.
A comparative study of the three sites revealed that a total of
734.81 ha were mined between 1996 and 1999 in the Estevan area. Out of
this figure, 444.03 ha have been successfully reclaimed and
decommissioned (Table 2). Thus, 60% of the total area disturbed has been
levelled to the acceptable slope of less than 10%. The proportion of
levelling is an improvement over the situation that existed before the
1993 Guidelines were developed when virtually nothing was done. However,
there was a shortfall in the rate of seeding. Only 17% of the total area
disturbed has been seeded which is equivalent to 29% of the total area
levelled. The problem is attributed to the harsh climate and soil
conditions of the area as well as equipment problems. Nevertheless,
portions of the three sites met SE's minimum standards and the
mining company has been released from further responsibilities of
restoration on these lands.
Overall, Boundary Dam Mine recorded the largest area mined between
1996 and 1999, accounting for 46% of the total area disturbed.
Similarly, the area rehabilitated was the highest of the three sites
studied. This was due to the commitment of more equipment and personnel
to rehabilitation activities during that period, as compared to the
other sites. Between two and five bulldozers were used in restoration
practices depending on the site-specific requirements of the area. An
equal number of personnel was also employed. The Utility Mine recorded
the second highest rate of disturbance after Boundary Dam Mine (Table
2). Out of the total area of 208.41 ha mined at the Utility Mine
(1996-1999), 136.97 ha have been successfully graded accounting for 31%
of total area levelled in the Estevan area.
Table 2 provides a comparison of the rates of disturbance, leveling
and seeding among the three mine sites. Bienfait Mine recorded the least
amount of area mined (189.13 ha) and restored during the period. The
area levelled at the Bienfait Mine accounted for 29% of the total area
levelled in the Estevan area. Aerial orthophoto map interpretation
confirmed the spatial-temporal variation in the rate of disturbance and
rehabilitation at the Boundary Dam, Utility and Bienfait Mines over the
years. About 60% of the levelled areas met SE's standards and were
released from reclamation obligations. SE inspectors consider the
overall rate of leveling as average.
Local Residents' Perceptions of Ecological Rehabilitation
COPYRIGHT 2006 Wilfrid Laurier
University Reproduced with permission of the copyright holder. Further reproduction or distribution is prohibited without permission.
Copyright 2006, Gale Group. All rights
reserved. Gale Group is a Thomson Corporation Company.
NOTE: All illustrations and photos have been removed from this article.