Evaluating collaborative planning: a case study of a
Land and Resource Management Planning process.
by Gunton, Thomas I.^Peter, Thomas^Day, J.C.
In October 2000, the B.C. government gave a March 2001 completion
deadline to the planning table to complete the first phase of the plan.
In an effort to meet the deadline, the planning table tried to develop a
plan acceptable to all stakeholders through intensive negotiating
sessions using a two-phase approach. Phase one was to develop
recommendations on the main land use management issues, and phase two
was to finalize management decisions and establish strategies to
implement the plan (BC MSRM 2004). Two different plans were established
during these sessions: one from the resource extraction group and one
from the conservation/recreation group. One week before the deadline,
stakeholders agreed that consensus on one plan was not possible (Mou
2003).
This impasse led the stakeholders to accept a "final offer
selection" process in which each of the two groups would propose
its final plan to the B.C. government in the form of an offer (BC MSRM
2004). Consequently, the Lillooet LRMP table submitted two separate land
use scenarios to the B.C. government in March 2001 (BC 2001). The first
scenario was proposed by the coalition of Lillooet communities (CC) and
the second by the conservation, recreation, tourism, and community group
(CRTC). The two plans were similar in structure, including a summary of
the main objectives, strategies, maps, and background information on the
Lillooet area. The principal difference in the plans was the proportion
of the land base designated as protected areas: 15.7% in the resource
sector proposal and 18.8% in the conservation sector proposal. The
conservation sector proposal was forecast to result in a 14.5% reduction
in the timber harvest compared to a 10.8% reduction in the resource
sector proposal (BC MSRM 2001). It is interesting to note that the final
offer selection process had reduced the range of difference in the two
final offer proposals to 3.1%, which is considerably lower than the
range of difference among the earlier proposals of 18%.
In April 2001, the government completed phase one of the Lillooet
process to designate land use zones by approving the conservation
proposal to protect 18.8% of the land base. The government announced
that phase two of the Lillooet process to prepare more detailed
management plans for resource extraction would be completed by March
2002 (BC 2001). However, a new government elected shortly after the
decision to accept the conservation scenario cancelled the approval and
directed government staff to prepare a new plan. The government cited
community concerns over the plan as the rationale for the rejection of
the plan approved by the previous government. This is the only case in
which a plan proposal submitted from an LRMP process was rejected by the
government. Another important change that occurred subsequent to the
April 2001 decision was the accumulation of court cases that
strengthened the obligation of government to consult and accommodate
First Nations in any decisions affecting First Nation interests (Donovan
and Griffith 2003). The lack of consultation with First Nations in the
2001 Lillooet LRMP decision therefore could potentially undermine the
legal basis of the decision.
Following consultation with public and First Nations, the Ministry
of Sustainable Resources Management prepared a new draft land use plan
for Lillooet in 2004 (Figure 1). A major difference between the new plan
prepared for discussion by the government and the original plan approved
by the government in April 2001 is a reduction in protected areas from
18.8% in the original plan to 17% in the new plan (BC MSRM 2004). The
major proportion of this reduction--1.3% out of the 1.8% reduction--is
due to a reclassification of a section of the major new park proposal,
Spruce Lake, from "protected" to a new zone that would allow
tourism and mining while maintaining the prohibition on logging. The
remaining 0.5% decline is due to reduction in other protected area
proposals. As of March 2007, the draft plan is still being discussed
with First Nations (Jim Britton, personal communication, March 22,
2007). During discussions, no resource development is allowed in
proposed protected areas.
Evaluation Methodology
The methodology used to evaluate the planning process is based on a
multiple criteria evaluation framework developed by the Sustainable
Planning Research Group at Simon Fraser University and used in the macro
analysis of the twenty-one land use plans in British Columbia (Frame et
al. 2004). The evaluation criteria include eleven outcome criteria and
fourteen process criteria (Table 3 and 4). The criteria were developed
by integrating and enhancing evaluation frameworks proposed by Innes and
Booher (1999), Cormick et al. (1996), Moote et al. (1997), and Williams
et al. (1998). The eleven outcome criteria are based on four broad
measures of success: reaching an agreement, reaching an agreement that
is in the public interest, using a planning process superior to
alternative processes, and generating "social capital"
benefits such as improved stakeholder relationships and knowledge. The
fourteen process criteria are based on best practices planning criteria
based on Innes and Booher (1999), Cormick et al. (1996), Moote et al.
(1997), and Williams et al. (1998).
Assessing the degree to which the planning process meets the
criteria is based on stakeholder ratings derived from a survey for all
criteria except reaching agreement. The reaching agreement criterion is
assessed by examining the outcome of the planning process based on
planning process records. The stakeholder survey uses multiple questions
to evaluate each criterion: twenty-four questions are used to evaluate
the ten outcome criteria and forty-six questions to evaluate the
fourteen process criteria. The questions in the survey are based on
statements with which stakeholders agree or disagree using a four-point
Likert type scale of strongly agree, somewhat agree, somewhat disagree,
and strongly disagree. For purposes of presentation, the strongly agree
and somewhat agree responses are combined as agree and the average for
all questions under each of the twenty-four criteria is calculated to
report the degree of agreement by criterion. Open-ended questions are
also used to assess stakeholder perceptions of the strengths and
weaknesses of the process. A coding system is used to categorize
responses and calculate the frequency of each type of response. Those
wishing to review the survey and methodology in more detail should
consult Frame et al. (2004).
Results
A total of forty-eight participants were identified to be surveyed:
thirty-four table participants, ten alternates, and four process staff.
Of the forty-eight targeted participants, thirty-three were sent surveys
by email or mail. No contact information was available for the remaining
fifteen participants. Responses were received from sixteen participants,
for a response rate of 33% of potential respondents and 45% of those
contacted. Respondents represented all key groups including support
staff, government, resource development, and conservation sectors.
Responses were received during March 2005 and are therefore perceptions
of stakeholders of the process structure and outcomes as of that date.
Responses for the outcome criteria are summarized in Table 5. To
date, the criterion of reaching agreement on a plan has not been met.
However, it is important to note that the planning table did achieve a
consensus agreement on a process to accept the outcome of a final offer
selection based on two submissions to the government. In this sense the
planning process did achieve a consensus outcome that was subsequently
rejected by the government, the first such rejection in the history of
the LRMP process. It is also important to note that, although the
process has not yet resulted in a final plan outcome, the process has
been successful in narrowing the range of disagreement among the
parties. As noted earlier, the range of difference in the options for
protected areas was reduced from 18% of the land base in 1999 to 3.3% in
the final offer plan options submitted in 2001. The 2004 government
draft plan recommends protected areas within the range between the two
final offers submitted in 2001. Therefore the process has been
successful in significantly reducing disagreement among stakeholders and
increasing the likelihood of achieving an outcome acceptable to all
parties.
Two other criteria were also not met: achieving an outcome that met
the interests of the stakeholder group (25% agreement) and reducing
conflict (19% agreement). However, more than one-half of respondents
(56%) agreed that the outcome to date has been in the public interest.
The process has also been very successful in generating additional
social capital benefits including: improved knowledge (94%), creative
ideas (88%), improved relationships among stakeholders (75%), and useful
information (75%). The strength of the process in generating social
capital was also the achievement most frequently cited by respondents in
the unprompted, open-ended questions (frequency of 38%). The process of
collaborative planning was perceived as superior to alternative methods
by 75% of respondents. The consensus-based, multistakeholder approach
was also cited most frequently by respondents as a strength of the
planning process in the open-ended responses (frequency of 75%).
COPYRIGHT 2006 Wilfrid Laurier
University Reproduced with permission of the copyright holder. Further reproduction or distribution is prohibited without permission.
Copyright 2006, Gale Group. All rights
reserved. Gale Group is a Thomson Corporation Company.
NOTE: All illustrations and photos have been removed from this article.