ENGINEERING MANAGERS ARE CHALLENGED TO MEET increasing energy
demands while holding the line on energy costs. The $1 trillion 2006
energy cost went up $200 billion from 2005, and power consumption in the
United States has increased almost without interruption for more than
five decades (Figure 1).
The energy users in your facility are the standard and special
electrical components arranged in a unique physical layout linked
together by the power distribution system. In many facilities, the exact
arrangement is not well-known because the distribution system blueprints
or schematics are lost or systems have been altered over time without
documentation.
This is a very common but serious disadvantage to an industrial,
maintenance, or engineering manager seeking improvement opportunities:
You have to know what you have before you can make it better and measure
the gain. Measurement must come before control.
Do you know where the top energy users are in your facility and how
much energy they consume? Even if you're confident about this, an
annual audit may be in order to guard against creeping change. The first
step to starting or upgrading a power monitoring system is to gather all
system layout information. It's necessary to check all information
by walking the system and marking up the old electrical distribution
system schematics, noting the additions and modifications. If you do not
have the original drawings, there are standard power distribution system
layout sheets available from your electrical equipment vendor or
electric utility company representative that can be used to simplify the
process and ensure that no key components are omitted.
The best place to start documenting the power distribution system
layout is at the incoming power service entrance. This is where the
power company high voltage service enters your facility, passes through
a high voltage switch in the substation, then continues through a
step-down transformer where the voltage is stepped down to the highest
voltage distributed in your facility (typically 440 volts). From here
the power distribution system branches out into one or more feeder
circuits. Typical groupings of power users are boiler and steam systems;
building heating and cooling; compressed air; data centers; hot water;
lighting; plant operating equipment, motors, and drives; refrigeration;
and security systems. Each feeder may be divided into several branch
circuits, which provide electric power to individual equipment items
such as HVAC drive motors, lighting, heating devices, computer services,
and operating equipment. The layout should show each circuit and the
equipment served, along with nameplate information such as volts, amps,
horsepower, cycles, and design factor for each item.
[FIGURE 1 OMITTED]
As an alternative to preparing a blueprint schematic of your power
distribution system, you can use a CAD system software package--one that
has electrical symbols in the database, such as AutoCAD or Microsoft
Visio--and create an up-to-date schematic (Figure 2). These tools have
the advantage of quick and easy revision. Thus, if you add to the system
or move equipment around as needs change, you have a much better chance
of keeping the layout current because it is so much easier and quicker
to do. The discipline to enter each field change when it is implemented
must be maintained by making this documentation a step in the job
content of the work order authorizing the change.
[FIGURE 1 OMITTED]
Cost control panel
Power savings come from two sources: demand rate reduction and
lower energy consumption. Demand rate is the rate per kilowatt-hour
(kw-hr) charged by the power company. This rate is based on the peak
demand that occurred during the period in which your rate was
calculated. The higher that peak demand was and when it occurred
determines the rate you pay your electric utility company for all of
your power during the following contract period. The energy consumption
is the cumulative kw-hrs consumed during the billing period. The more
kw-hrs consumed, the greater the power bill.
Both rate and consumption are controllable expenses and the
resulting energy cost can often be reduced by 20 percent with good power
management as opposed to low or no power management. Lowering your peak
demand or shifting your peak demand away from the power company's
peak demand time of day lowers your rate. Lowering consumption by
installing more energy-efficient electrical devices lowers your
consumption.
The next step, after system documentation, is to upgrade the power
monitoring program to evaluate the system you have documented and assess
the opportunities. Where would the monitoring likely provide the most
benefit? The main service entrance switch gear is usually metered by the
power company or in-house if you generate your own power. These sources
give the overall load but don't detail the individual loads that
contribute to it. To obtain a breakdown, install some form of temporary
or permanent sub-metering on each feeder circuit. These sub-meters will
show which feeders use the largest lighting, motor, and heating loads.
Sub-metering individual branch loads will identify specific electrical
equipment where the most potential savings may be gained. An individual
motor load can be measured by simply clamping an ammeter, also called a
tong tester, on each of the phases at the line switch. By sorting the
loads in descending order, you can create a Pareto analysis (for
example, 80 percent of the load may be concentrated at 20 percent of the
equipment) that highlights the best savings opportunities.
Energy consumers want to improve benefits from energy consumed,
reduce life cycle costs, and keep the system reliable. Factors you want
the meters to identify are peak demand amount and time of day, source of
the highest demands, and disturbances that might cause critical
interruptions or power quality problems. Power meters basically measure
volts and amps and convert the readings internally to other metrics such
as power factor--a measure of the efficiency of the power delivered. The
lower the power factor, the greater are the losses (reactive kilovars)
and the more you pay for the same useful power. For example, induction
motors tend to lower power factor, sometimes to as low as 80 percent.
Induction motor circuit power factor is corrected toward unity (PF = 1,
or 100 percent) by inserting variable power factor correction capacitors
into the circuit that automatically adjusts power factor. Depending on
the variations read by the meters, power factor can be increased to the
high nineties, saving a lot of energy while reducing the peak demand if
the related equipment is the cause of the peak demand. This adjustment,
therefore, has the potential to save both the total amount used and the
rate paid.
The same meters that detect peak demand and power factor can be
used to track disturbances and energy cost by department, tenant,
process or output. They can also automate load control and load
management. By tying the system into your building management system,
you can more easily monitor both systems and integrate several systems
spread over one or more states so that all systems and the total energy
consumption of all facilities can be monitored from one central point,
such as a corporate headquarters.
Meters have integrators that store readings so that in the event of
a power interruption, no data is lost. When power returns, the data
stored is accessed and logged.
[FIGURE 2 OMITTED]
Coherent energy strategy
The power management meters and sub-meters comprise the system
hardware. Coupled with the software, it provides a powerful energy data
collection and control system. Each meter represents a measurement and
control point. The data from that point is fed back to the computer,
converted into the various metrics being measured, and displayed on a
real-time graphic display at one or several control points. The graphic
shows the power distribution system. Each control point is represented
symbolically and, next to the symbol, a data display box registers the
real-time variation in kilowatts at that point as well as other metrics
that were selected. The meters are scalable to allow adding more metrics
and reading them at more or less frequent intervals as required.
Having completed the specification of power distribution monitoring
upgrades, you now have a list of several important training
opportunities. This list is in the form of your bill of material for the
upgrade along with the new schematic of your power distribution system.
You can use the schematic to bring all the electricians who work on the
system up-to-date on the current layout and point out the current load
balance situation--where there are bottlenecks in the capacity that
limit further loads on that phase, feeder, or branch and where further
loads are sufficient. You can also begin, just by inspection of the load
distribution, to make improvements to reduce the load such as premium
efficiency motors and low-wattage lamps replacing older, less efficient
ones.
If you have introduced new CAD electrical distribution software,
now is a good time to broaden familiarity with it so that more than one
person in the organization can update it or retrieve sections for
planning purposes.
COPYRIGHT 2008 Institute of Industrial Engineers,
Inc. (IIE) Reproduced with permission of the copyright holder. Further reproduction or distribution is prohibited without permission.
Copyright 2008 Gale, Cengage Learning. All rights
reserved. Gale Group is a Thomson Corporation Company.
NOTE: All illustrations and photos have been removed from this article.