In 2007, MIL-STD-461 turned 40 and Version F was released on Dec.
10. MIL-STD-461F includes changes as a part of normal evolution to
update requirements and methods to more closely evaluate products for
the changing electromagnetic environment.
The new method restores a test that was deleted by the release of
MIL-STD-461D in 1993. Changes in the standard may be significant when
qualifying products to the now current revision. In conjunction with the
release of MIL-STD-461F, three Data Item Description (DID) documents
were released.
Here is a clause-by-clause review of the standard where differences
between the E and the F versions are notable.
Interchangeable Modular Equipment (4.2.7)
A new item in MIL-STD-461F requires qualification of assemblies
when new line replaceable modules (LRMs) are incorporated into devices.
The qualification can be by test or similarity assessment but requires
approval of the procuring agency.
Construction and Arrangement of EUT Cables (4.3.8.6)
"Input power leads, returns, and wire grounds shall not be
shielded." This requires breaking out the power leads that are part
of a cable bundle shielded for the test (4.3.8.6.2).
In 1993, MIL-STD-461D definitively established the requirement to
test with cables of the type used in the installation. This was a major
move to force responsibility for EMI/EMC control into the hands of the
integrator/supplier or whoever had providence over the interconnecting
and power cables.
This revision removes the capability to shield power cables as an
EMI control measure because, in most installations, shielded power
cables are not the norm. An exception is discussed (A4.3.8.6) where
filtered power is provided from another device: Shielding may be
supported.
In addition, shielded cables for Navy surface ship applications may
allow an unshielded section for radiated tests but not for conducted
testing. The test configuration needs to be described in the test
procedure and approved by the procuring agency. But basically for most
applications, the power cables should be unshielded.
Computer Controlled Instrumentation (4.3.10.2)
Verification of software needs to be described in the test
procedure. For commercial software, identification of the manufacturer,
model, and revision must be provided. For locally developed software,
the control and methodology must be indicated.
This presents a challenge for test-procedure developers who
aren't part of the designated test laboratory. The laboratories
should prepare the necessary documentation and make that available to
procedure writers to support designation of the test laboratory.
Bandwidths (4.3.10.3.1)--Alternate Scanning Technique
"Multiple faster sweeps with the use of a maximum hold
function may be used if the total scanning time is equal to or greater
than the Minimum Measurement Time defined ...," referring to the
measurement time found in Table II. This may give an impression that the
test duration can be reduced, but clearly that is not the intent.
The discussion in the appendix indicates that the faster sweep
allows for capture of low duty-cycle or intermittent signals. However,
in section 4.3.10.3.3, the scanning rate must be adjusted to capture
infrequent emissions.
To assure capture, the overall scan needs to be at every one-half
resolution bandwidth over the EUT cycle. Realizing that signals such as
frequency-hopping modulations would require an exceptionally long sweep
for all of the energy to be quantified, don't hesitate to use the
faster sweep with multiple max-hold capture to show the envelope of this
type of signal.
Frequency Scanning (4.3.10.4.1)
The susceptibility sweep rate or step size has been increased for
frequencies above 1 GHz, allowing a faster susceptibility test. This
change of sweep rate or step size reduces the test time even with a long
EUT cycle time since the cycle time affects the dwell period and not the
step.
Thresholds of Susceptibility (4.3.10.4.3)
MIL-STD-461F adds a statement, "Susceptibilities and anomalies
that are not in conformance with contractual requirements are not
acceptable. However, all susceptibilities and anomalies observed during
conduct of the test shall be documented." What is the implication?
It is not unusual to test hot--at levels above that required. And
the possibility exists to observe an anomaly at the elevated test levels
only to find that the anomaly is not present when the correct test level
is applied to the EUT. This new statement requires documentation of all
observed, albeit compliant, anomalies.
Emission and Susceptibility Requirements, Limits, and Test
Procedures (5.3)
A new CS106, formerly identified as CS06 in MIL-STD-461C and
dealing with voltage spikes on power input lines, is listed in Table IV.
The applicability list of Table V includes a few changes in applications
associated with some of the test methods such as CE101, CS109, CS115,
CS116, and RS101.
CEIOI (5.4)
Applicability has been added to surface ships. In addition, the
appendix provides some tailoring guidance for high current loads or
certain wiring considerations. Suggestions are made for the use of a
5-[micro]H line impedance stabilization network (LISN) and limit
adjustments with frequency range changes.
MIL-STD-461 has long supported tailoring for several revisions, but
this represents one of the few specific suggestions for tailoring. The
tailoring falls on the procuring party, but a test plan could recommend
the tailoring for approval by the procuring party. Calibration
verification with all test equipment including cables, probes,
attenuators, amplifiers, and receivers is accomplished prior to test. If
multiple limits for different power inputs are specified, use the most
restrictive limit to demonstrate.
CE102 (5.5)
No changes in the requirements except the tailoring regarding
Section 5.4 affects CE102.
CE106 (5.6)
Testing of both the receive and the standby mode is unchanged. The
CE106 transmitter limit for the 2nd and 3rd harmonics was redefined to a
level of -20 dBm (87 dB[micro]V) or 80 dB below the fundamental,
whichever requires the least suppression. All other harmonic and
spurious emissions must be suppressed by 80 dB.
Assuming a 100-W (50 dBm, 157 dB[micro]V) transmitter, the
suppression would be 70 dB to achieve the -20 dBm level for the 2nd and
3rd harmonics and 80 dB for all other frequencies. Making this
measurement requires a dynamic range sufficient to show compliance to
the limit.
Other issues include determining the frequency span associated with
the harmonic emissions. How is the transmitter output power verified
since in-band testing is not required? How is the fundamental suppressed
without sacrificing sensitivity at out-of-band frequencies? Is the power
in the harmonics sufficient to cause nonlinearity in the detection
system? How do you handle connection to a transmit port with a type N
connector during testing up to 40 GHz?
These are some of the questions that need to be addressed prior to
testing--typically during test-procedure development--so both the right
equipment and test approach are in place to support the test. Be
prepared for several hardware configurations and the associated
calibration verification.
CSI0I (5.7)
While there are no changes in the requirements, don't forget
the capacitors. The higher-frequency losses in the LISN without the
capacitors are fairly dramatic and result in a significant undertest.
Make all personnel aware of the potential for shock hazards from the
isolated oscilloscope configuration.
CS103, CS104, CS105 (5.8, 5.9, 5.10)
There are no changes in the requirements because the testing has
been a tailored requirement in the contract for a long time. This test
normally calls for a lot of preparation to achieve the test method and
limits. Often, the procedure is developed as part of the contract
preparation, and if not, the procedure and limits are developed and then
added to the contract through test-procedure approval.
CS106 (5.11)
This is a new requirement that brings power-line voltage transient
testing back into the requirements for some applications. It restores
CS06 testing from MIL-STD-461C, superseded in 1993, but with only one
pulse duration.
The details are spelled out in the standard, but basically the
5-[micro]s pulse at 400 V is precalibrated into a noninductive 5-[ohm]
resistor. That generator setting is used as the maximum applied if the
400-V pulse is not generated during the test with a lesser generator
setting.
The waveform characteristics are very well defined, and some of the
older spike generators are not adequate for the specification. Once the
generator level is calibrated, the positive and negative transients are
applied to all ungrounded power inputs between phases or between the
phase/positive and the neutral/return.
The application between the chassis and phase/positive is not
applicable. The test duration is 5 minutes with a 5- to 10-pulse/s
repetition rate for each polarity. Unlike the old CS06, phase
synchronization is not applicable. Again, watch for the shock hazard
with the ungrounded oscilloscope.
CS114 (5.13)
The testing is basically the same with an additional common-mode
test for power leads in the 4-kHz to 1-MHz frequency range for some
applications. Here is a refresher on the process because often it is
accomplished incorrectly:
* Precalibrate the applicable calibration curve levels to establish
a maximum forward power level for the test-frequency range. The standard
also reminds us to use the same hardware as used for the calibration.
COPYRIGHT 2008 Nelson
Publishing Reproduced with permission of the copyright holder. Further reproduction or distribution is prohibited without permission.
Copyright 2008 Gale, Cengage Learning. All rights
reserved. Gale Group is a Thomson Corporation Company.
NOTE: All illustrations and photos have been removed from this article.