Understanding strategic bidding in multi-unit
auctions: a case study of the Texas electricity spot
market.
by Hortacsu, Ali^Puller, Steven L.
(13) Observe that we have not imposed independence on this joint
distribution; contract quantities and demand noise can be correlated.
However, as will be evident from the bidder's objective function
below, this is not a common value environment, as other bidders'
contract quantities do not enter into the bidder's ex post utility.
(14) The proof can be found in Hortacsu and Puller (2005).
(15) Although this is a comforting result from the perspective of
assuming differentiable bid schedules, Kastl (2006a) finds that if
bidding extra points is a costly activity, the constrained optimal
bidding behavior may depart significantly from equation (2). We discuss
some evidence regarding this possibility in Section 5.
(16) Some of these assumptions and possible estimation strategies
based on such assumptions are discussed in the discriminatory
(pay-as-bid) share auction context by Hortacsu (2002a).
(17) The primitives of this game are the set of firms that are
participating, N, their cost curves [C.sub.it](q), i = 1, ..., N, the
joint distribution of contract quantities, and the distribution of the
uncertain demand component.
(18) The additive separability restriction appears to be crucial.
Note that without this separability restriction, we cannot, in general,
collapse the stochastic terms (from the perspective of bidder i) into a
single scalar random variable. See Appendix A for further discussion of
the case where private information leads to rotations in residual
demand, as opposed to shifts.
(19) In particular, for certain specifications of marginal costs, a
bidder's best-response to additively separable bidding strategies
by her opponents may not be additively separable.
(20) This could be extended to show that given [QC.sub.i], one can
compute the entire marginal cost curve rationalizing a supply curve
[S.sub.i](p) observed in the data using a single realization of the
residual demand curve.
(21) Notice that the lumping of the day-ahead quantity and the
balancing bids does not affect the strategic nature of the game because
the bidders are not provided any information about each others'
actions until the market clears.
(22) One could be concerned that there is a small set of distinct
contract quantities; however, the empirical distribution we recover
using Proposition 1 suggests that our assumption of a continuous
differentiable distribution of contract quantities is very reasonable.
(23) Let {([p.sub.1], [q.sub.1]), ..., ([p.sub.K], [q.sub.K])
represent the price and incremental quantities that form the residual
demand curve seen in the data. The smoothed version of this function is
RD(p) = [[sigma].sup.K.sub.k=1] [q.sub.k][kappa] (p - [p.sub.k]/h),
where [kappa](.) is a kernel function. With this representation, the
derivative of residual demand is RD'(p) = [[sigma].sup.K.sub.k=1]
[q.sub.k] 1/h[kappa]' (p - [p.sub.k]/h). We used a normal kernel
and the smoothing parameter, h = 10 MW throughout our analysis.
(24) As an illustration, Reliant's expost profitability is 79%
under "smoothed" residual demand and 70% under the grid
search.
(25) Some hydroelectric units may be able to respond to balancing
calls; however, these units represent less than 1% of total capacity and
are primarily owned by the Lower Colorado River Authority.
(26) We cannot use a measure such as the fraction of possible
profits achieved because some firms tend to be short on their contract
positions entering the balancing market, and we would have to make an
assumption about the contract price. The measure we construct
differences out the contract price and avoids this complication.
(27) Note that two firms, Extex Laporte and Air Liquide, earn lower
profits under actual bidding than bidding to "avoid the
market." Both firms, which are infrequent participants in the
balancing market, have positive contract positions and relatively
high-cost units available. Both bid so they are called to INC despite
the fact that it would be more profitable to not participate and buy its
contract position from the market at a price lower than marginal cost.
(28) Note that individual firm bid data are only available (to
firms and analysts) with a six-month lag, so firms are unable to use
Proposition 1 in real time to estimate rival firms' contract
quantities and resolve some of their uncertainty. Some of rivals'
uncertainty stems from variation in [QC.sub.it]. We find that balancing
contract positions by a firm varies across time; for example, the
standard deviation of [QC.sub.it] is 449, 161, and 7 for Reliant,
Calpine, and Guadalupe, respectively.
(29) We discuss this sample further in Section 5.
(30) An annual expenditure of $1 million corresponds to $114 per
hour for one year of operations (365 days, 24 hours), without correcting
for the fact that the hour we are analyzing is a peak hour.
(31) We also used a similar approach to get a lower bound on the
implied cost of using an additional bid point. To do this, we calculated
TXU's NBR profits using 12 versus 13 bid points (we kept the 12
equally spaced points constant, and varied the 13th point to maximize
TXU's profit). TXU's incremental profit gain from adding the
13th bid point was $1.59.
(32) It is difficult to make a direct comparison between
"rounds" in the laboratory and "days" in electricity
markets. However, if we are willing to equate rounds with days, bidding
behavior appears to converge (in percentage profit terms) to theoretical
predictions quicker in many laboratory experiments. See Kagel (1995) for
examples from auction experiments.
(33) Because total demand is perfectly inelastic, prices higher or
lower than competitive levels do not cause suboptimal levels of
consumption. All inefficiencies are productive rather than allocative.
For a more general discussion of the efficiency properties of uniform
price multi-unit auctions, see Ausubei and Cramton (2002).
(34) Borenstein, Bushnell, and Wolak (2002) find the actual
production costs to be 14% higher than competitive levels in the
California market in 2000. Mansur (forthcoming) refines the methodology
and finds that production costs in the PJM market exceed competitive
costs by 3%-8%. Note that our analysis only calculates productive
inefficiencies in the balancing market for units that have already
started and submitted day-ahead schedules.
(35) Note that the "reverse" of this counterfactual,
where we set nonstrategic bids equal to marginal cost and do not allow
strategic bidders to respond, would be less realistic, because our
results show that the strategic bidders do respond to changes in the
residual demand they are facing. Counterfactuals involving the
equilibrium response of strategic bidders are complicated by the fact
that multi-unit auctions can have multiple equilibria.
Ali Hortacsu *
and
Steven L. Puller **
* University of Chicago and NBER; hortacsu@uchicago.edu.
** Texas A&M University; puller@econmail.tamu.edu.
TABLE 1 Outcomes under Actual, Ex post
Optimal, and Naive Best-Response Bidding
Percent Achieved
Relative to
XP Optimal Naive BR
Firm (1) (2)
Reliant 79% 80%
Brownsville PUB 50% 50%
City of Bryan 45% 45%
Tenaska Gateway Partners 41% 41%
TXU 39% 41%
Calpine Corp 37% 38%
Denton Municipal Electric 35% 35%
Ingleside Cogeneration 31% 31%
City of Austin 30% 31%
Rio Nogales LP 28% 28%
Lower Colorado River Auth 25% 25%
City of San Antonio 23% 24%
Gregory Power Partners 20% 20%
Midlothian Energy 17% 17%
Cogen Lyondell Inc 16% 16%
Tractebel Power Inc 16% 16%
Brazos Electric Power Coop 15% 15%
Lamar Power Partners 15% 15%
Mirant Wichita Falls 14% 14%
BP Energy 14% 14%
City of Garland 13% 13%
Hays Energy 8% 8%
West Texas Utilities 8% 8%
Central Power and Light 8% 8%
Guadalupe Power Partners 6% 6%
Tenaska Frontier Partners 5% 5%
South Texas Electric Coop 3% 3%
Sweeney Cogeneration 2% 2%
Brazos Valley Energy LP 0% 0%
AES Deepwater 0% 0%
Frontera General LP 0% 0%
TGC 0% 0%
South Houston Green Power 0% 0%
Air Liquide America -8% -8%
Extex Lanorte LP -81% -81%
Producer Surplus
($/hour)
COPYRIGHT 2008 Rand, Journal of
Economics Reproduced with permission of the copyright holder. Further reproduction or distribution is prohibited without permission.
Copyright 2008 Gale, Cengage Learning. All rights
reserved. Gale Group is a Thomson Corporation Company.
NOTE: All illustrations and photos have been removed from this article.