The hierarchy [H.sub.1] is the most profitable for the principal
among all delegation hierarchies with the same observability
assumptions, because it endows the principal with the broadest possible
contracting abilities. In particular, the principal signs a contract
with the primary contractor and receives her cost report before the
latter communicates with the subcontractor. Therefore, [H.sub.1] serves
as a natural benchmark establishing what is attainable in a delegation
mechanism. This hierarchy provides a good representation of contractual
schemes in the construction industry where the customer, first, hires a
primary contractor and obtains a cost estimate from her. The primary
contractor is then typically given the authority to subcontract other
providers whose costs are ex ante uncertain.
By the Revelation Principle, the two-agent mechanism is at least as
profitable for the principal as [H.sub.1]. So the questions are whether
the principal can achieve the same expected profits in [H.sub.1] as in
the two-agent mechanism, and how [H.sub.1] compares to the single-agent
mechanism. An answer to these questions is provided in the following
proposition. Before presenting it, let us introduce the following piece
of notation. Recall that the quantity schedule in the optimal two-agent
mechanism is denoted by [{[q.sup.i.sub.LL], [q.sup.i.sub.LH],
[q.sup.i.sub.HL], [q.sup.i.sub.HH]}.sup.i=2.sub.i=1]. Let
[[bar.q].sub.i] = max{[q.sup.i.sub.LL], [q.sup.i.sub.LH]} and
[[q.bar].sub.i] = min{[q.sup.i.sub.HL], [q.sup.i.sub.HH]}.
Proposition 5. If agent i [member of] {1, 2} serves as the primary
contractor, then the principal obtains the same payoff in [H.sub.1] as
in the two-agent mechanism if [absolute value of [v.sub.12]([q.sub.1],
[q.sub.12])/[v.sub.11]([q.sub.1], [q.sub.2])] [less than or equal to]
1/1 - [p.sub.j], i [not equal to] j, for all ([q.sub.1], [q.sub.2])
[member of] [[[q.bar].sub.1], [[bar.q].sub.1]] x [[[q.bar].sub.2],
[[bar.q].sub.2]]. Conversely, the hierarchy [H.sub.1] with agent i
[member of] {1, 2} as the primary contractor is strictly less profitable
for the principal than the two-agent mechanism if [absolute value of
[v.sub.12]([q.sub.1], [q.sub.12])/[v.sub.11]([q.sub.1], [q.sub.2])] >
1/1 - [p.sub.j], i [not equal to] j, for all ([q.sub.1], [q.sub.2])
[member of] [[[q.bar].sub.1], [[bar.q].sub.1]] x [[[q.bar].sub.2],
[[bar.q].sub.2]].
If either agent can serve as the primary contractor, then the
principal obtains the same payoff in [H.sub.1] as in the two-agent
mechanism in the following cases: (i) under complementarity; (ii) under
substitutability, if [v.sub.iii](x) [greater than or equal to] 0,
[v.sub.iii] [less than or equal to] 0, and [v.sub.ijj] [greater than or
equal to] 0 for some i [not equal to] j and all ([q.sub.1], [q.sub.2])
[member of] [[[q.bar].sub.1], [[bar.q].sub.1]] x [[[q.bar].sub.2],
[[bar.q].sub.2]].
[H.sub.1] is strictly more profitable for the principal than the
single-agent mechanism if IC(LL - HH) is binding in the latter.
According to Proposition 5, if only one of the agents can serve as
the primary contractor, then [H.sub.1] is equivalent to the two-agent
mechanism when the interdependence between the inputs in their final use
is not too large, that is, the marginal benefit/product of one input is
not too sensitive to the quantity of the other input.
To understand this result, note that [H.sub.1] is equivalent to the
two-agent mechanism only if the principal can implement the quantity
profile from the optimal two-agent mechanism via [H.sub.1] at the same
expected cost. It is easy to see that in [H.sub.1] each agent obtains at
least as much surplus from private information regarding her own cost as
in the two-agent mechanism with the same quantity profile. So, [H.sub.1]
can only attain the same level of profitability as the two-agent
mechanism if the primary contractor cannot exploit her role as an
informational intermediary to earn additional surplus, and simply passes
on the information from the subcontractor to the principal without
manipulating it. Manipulating this information could be profitable for
the primary contractor for two reasons: (i) she could appropriate part
of the informational rent that the principal intends for the
subcontractor; (ii) she could extract more surplus from her own
information.
In hierarchy [H.sub.1], option (i) is infeasible because the
primary contractor has to report her cost type before communicating with
the subcontractor. Given the primary contractor's report, the
informational rents on the subcontractor's information can be
appropriated only by the subcontractor. However, option (ii) becomes
significant when the report regarding the subcontractor's cost has
a large effect on the quantity assigned to the primary contractor, which
is exactly when the degree of complementarity or substitutability
between the inputs is sufficiently large.
Specifically, suppose that the inputs are complementary and
consider the following deviation: the primary contractor misrepresents
her low cost as high in the first stage, and then always reports that
the subcontractor's cost is low, that is, in states LH and LL, the
primary contractor reports state HL. Then, in states LH and LL, the
primary contractor has to pay [C.sub.H][q.sup.2.sub.LH] to the
subcontractor, with a net loss of [DELTA]([q.sup.2.sub.LH] -
[q.sup.2.sub.HH]). However, the expected surplus obtained by the primary
contractor on the information about her own cost increases from
[DELTA]([q.sup.1.sub.HL] [p.sub.2] + [q.sup.1.sub.HH] (1 - [p.sub.2]))
to [DELTA][q.sup.1.sub.HL]. In the proof of Proposition 5, I show that
this increase outweighs the extra payment to the subcontractor when the
degree of complementarity is sufficiently large. This is so because a
report that the subcontractor's cost is low rather than high causes
a larger increase in the quantity supplied by the primary contractor,
and hence in her informational rent, than in the quantity supplied by
the subcontractor, and hence the extra payment to her. Then, in
[H.sub.1], the principal has to pay a larger informational rent to the
primary contractor than in the two-agent mechanism.
Under substitutability, the primary contractor with a low cost has
a strong incentive to announce that both costs are high, irrespective of
the subcontractor's cost. This incentive is similar to the extra
deviation factor and binding incentive constraint IC(LL - HH) in the
single-agent mechanism. The principal can offset this incentive to a
certain extent by imposing a penalty on the primary contractor when the
latter reports that both costs are high. Yet, this penalty cannot be too
large, because otherwise the primary contractor will misrepresent her
own high cost as low. As a result, the primary contractor's
incentive to overstate her cost cannot be mitigated when the degree of
substitutability is high, and again the principal has to pay a higher
informational rent in [H.sub.1]. (12)
If the principal can choose either agent to serve as the primary
contractor, then under complementarity she can always do so in such a
way that [H.sub.1] attains the same performance as the two-agent
mechanism. This is so because only one of the agents, when serving as
the primary contractor, can have an incentive to always report her cost
as high and the subcontractor's cost as low. (13) Under
substitutability, the ability of the principal to choose either agent to
serve as the primary contractor guarantees that [H.sub.1] is equivalent
to the two-agent mechanism only under additional restrictions on the
signs of the third-order derivatives of the benefit function, because
both agents could potentially have an incentive to overstate both costs.
Finally, the hierarchy [H.sub.1] performs better than the
single-agent mechanism if IC(LL - HH) is binding in the latter (which
could only happen under substitutability), because in this case the
principal can implement the optimal single-agent quantity profile at a
lower cost via [H.sub.1].
The hierarchy [H.sub.1] has two important properties affecting its
performance. First, in [H.sub.1] the primary contractor's decision
whether to report her true cost cannot be contingent on the
subcontractor's cost. This reduces the set of feasible deviations
by the primary contractor and benefits the principal. Second, only the
interim, rather than ex post, individual rationality constraints of both
agents have to be satisfied in [H.sub.1]. There is a significant
difference between these two types of constraints, in particular, as far
as the primary contractor is concerned. With the interim constraints,
the principal structures her contract with the primary contractor in
such a way that the primary contractor with a high cost obtains a
negative payoff for one realization of the subcontractor's cost,
and a positive payoff for a different realization of the
subcontractor's cost. However, this would be impossible if the
primary contractor's ex post individual rationality constraint had
to be satisfied, as would be the case, for example, if the primary
contractor could withdraw from the contract after receiving the
subcontractor's cost report.
COPYRIGHT 2008 Rand, Journal of
Economics Reproduced with permission of the copyright holder. Further reproduction or distribution is prohibited without permission.
Copyright 2008 Gale, Cengage Learning. All rights
reserved. Gale Group is a Thomson Corporation Company.
NOTE: All illustrations and photos have been removed from this article.