Abstract
Surface mining across the world has left a legacy of highly
disturbed landscapes. In a bid to reverse the trend of degradation,
various jurisdictions promulgated legislation and guidelines requiring
mine operators to rehabilitate disturbed lands for productive uses. This
paper examines the impact of regulations and guidelines on
rehabilitation practices at the Bienfait, Boundary Dam and Utility Mines
around Estevan, Saskatchewan between 1996 and 1999. This is a unique
case of mine rehabilitation with only one mining company and guidelines
designed for the site-specific conditions of the area. The paper
assesses reclamation success using both regulatory and social
indicators. The findings revealed that out of the 734.81 ha of land
disturbed during the years under review, 60% has been successfully
graded and 17% seeded. Both residents and regulators agreed that there
has been improvement in the quality, aesthetic, and safety outcomes of
restoration. However, the historical period studied revealed that
rehabilitation practices lagged behind the rate of mining due to
climate, personnel and equipment problems. Generally, Saskatchewan
Environment, the regulator, and local residents rated reclamation work
as average because they considered that it was not progressing fast
enough.
Partout dans le monde, l'exploitation de mines a ciel ouvert a
laisse en heritage des paysages fortement perturbes. Dans une tentative
de renverser cette tendance, diverses competences ont promulgue des lois
et des lignes directrices exigeant des exploitants miniers qu'ils
remettent en etat les terres pertur-bees a des fins productives.
L'auteur de cet article examine l'incidence des lois et des
lignes directrices sur les pratiques de remise en etat, entre 1996 et
1999, des mines Bienfait, Boundary Dam et Utility Mine a Estevan, en
Saskatchewan. II s'agit d'un cas exceptionnel de remise en
etat de mines touchant une meme entreprise miniere et ou les lignes
directrices ont ete concues expressement selon les conditions de la
region propres au site. L'auteur de l'article evalue le succes
de la remise en etat du terrain en se servant d'indicateurs de
reglemen-tation et d'indicateurs sociaux. Les resultats revelent
que, des 743,81 hectares de terres perturbees au cours des annees a
l'etude, 60 p. 100 ont ete niveles avec succes et 17 p. 100,
ensemencees. Les residents comme les organismes de reglementation ont
convenu qu'il y avait eu une amelioration de la qualite, de
l'esthetique et de la securite a la suite de la remise en etat.
Toutefois, au cours de la periode a l'etude, on a constate que les
pratiques de remise en etat accusaient un certain retard par rapport aux
activites minieres en raison de problemes lies au climat, au manque de
personnel et d'equipement. De maniere generale, Saskatchewan
Environment and Resource Management, l'organisme de
reglemen-tation, ainsi que les residents, estimaient qu'ils etaient
moyennement satisfaits des travaux de remise en etat, car ils
consideraient ceux ci n'avancaient pas suffisamment rapidement.
Keywords
Ecological rehabilitation, social evaluation, reclamation
regulation, reclamation guidelines, post-reclamation evaluation
Introduction
For decades, government regulatory agencies across the world have
grappled with the daunting task of formulating and enforcing regulations
and guidelines to address the problem of open pits and massive spoils at
mine sites. In China, wasteland produced by mining activities alone is
20,000 ha per annum (Marrs and Miao 2000). This is expected to exceed
33,000 hectares in the near future. Coal mining operations in the United
States have disturbed approximately 2.4 million ha of land since 1930
(Skousen et al. 1998). The contentious issue is that mining operators
desire to close mines and do not want to engage in a perpetual legacy of
repair and maintenance. Regulators on the other hand, resent the
situation that exists in Great Britain and elsewhere, where hundreds of
hectares of former coal lands are either undergoing land degradation or
act as a perpetual cost against host communities. Within close proximity
of mine lands, such communities are required to deal with thinning
soils, cracked drains and poor vegetation growth (Haigh 2002). These
controversies of mine degradation and reclamation share similarities
with challenges in Estevan, Saskatchewan, Canada.
Estevan is a major service centre for a large agricultural and
mineral-based region of southern Saskatchewan, about 200 km southeast of
Regina (Figure 1). It is often described as the 'Power Centre of
the Province' due to the large lignite coal deposits in the area. A
total of 5,582,845 tonnes of coal was produced in 1996 at the Boundary
Dam, Utility and Bienfait mines (City of Estevan 2000). The area of land
disturbed around Estevan is related to the magnitude of coal production.
Disturbed areas are characterized by spoil piles (piles of overburden
material), box cuts (which result in high walls on both sides of the
cut) and poor vegetation growth. Public outcry for a quality environment
and long-term sustain-ability of stressed lands led to an overhaul of
obsolete acts and the formulation of site-specific guidelines in 1993
and new regulations in 1996. The guidelines require the mine operator to
stabilize the spoil piles and to undertake reclamation simultaneous with
mining operations. The regulations provide Saskatchewan Environment (SE)
with the legislative authority to force industry to clean up the
existing backlog of disturbed lands in the area. Currently, both
guidelines and regulations apply to rehabilitation practices in the
Estevan area. However, the effectiveness of such regulations and
guidelines in compelling compliance is questionable. Stokstad (1998)
observes that while national programs to clean up abandoned mines have
existed for decades, this process has been haphazard and inefficient.
[FIGURE 1 OMITTED]
Against such a backdrop, this study assesses environmental
performance of mine operators in the Estevan area. The overall objective
of the paper is twofold; (1) to comment on the impacts of regulation and
guidelines on ecological rehabilitation practices by Luscar Mine, the
only mining company near Estevan, Saskatchewan; and (2) to examine the
perceptions of regulators and local residents regarding the extent of
rehabilitation practices in the area. In addition, this paper outlines
the strengths and weaknesses in the application of legislation and
guidelines in surface mine reclamation in the Estevan area between
1996-1999.
Frequently, the terms "restoration,"
"reclamation," and "rehabilitation" are used
interchangeably. Others argue that the terms have distinct meanings. The
Society for Ecological Restoration defines restoration as a
reinstatement of the original (pre-mining) ecosystem in all its
structural, functional and productive aspects or a process of restoring
nature to a perfect condition (SERM 1996, see also, Higgs 2003). Some
scholars (e.g. Harker et al. 1993) argue that "true"
restoration is almost impossible to achieve for both technical and
economic reasons. Reclamation refers to the process of returning the
mined site to a condition capable of supporting the same, or similar,
organisms that existed prior to mining (Friedlander 2001). Allen et al.
(2000) contend that rehabilitation involves creating an alternative
ecosystem following disturbance, different from the original and having
utilitarian (ecologically improved and socially acceptable) rather than
conservation values.
These distinctions have caused disagreement among environmental
practitioners and mine operators. Mine operators argue that they can
minimize surface-mining impacts by restoring mine lands to their
original contours, while creating loosely graded top soil for
non-compacted soil growth and planting native and non-competitive ground
covers and trees that will form early succession species for
wildlife--reclamation, by the foregoing definitions. Environmentalists,
however, have questioned the validity of these arguments on the grounds
that although it is aesthetically pleasing, the rolling, grassy hills do
not offer the same economic, environmental and ecosystem benefits as the
original forests or grasslands they replace, especially with respect to
preserving wildlife habitats and the ability to capture carbon from the
atmosphere.
Beyond the definitional quagmire of ecological rehabilitation, it
is important to note the progress that has been made in formulating
acts, regulations and guidelines for reclamation and the impacts of
these regulations on site-specific reclamation practices.
Evolution of Reclamation Acts in Canada
Regulations are enacted by parliament and generally have some
degree of force in law. They set out conditions for permit approval.
Guidelines may be informal directives to assist agencies in applying
regulations and reaffirming policy statements, or non-statutory
requirements. By their nature, guidelines are not legally binding in and
of themselves. Under an act or regulation, the proponent may be required
to follow a guideline, which must usually be attached as an appendix
since guidelines tend to change over time.
Alberta was the first jurisdiction to develop reclamation
regulatory policy with the enactment of the 1963 Surface Reclamation Act
(Alberta Environment 1999). In 1973, the concept of conservation was
introduced in the Land Surface Conservation and Reclamation Act. This
Act required operators to submit their plans for conservation and
reclamation and obtain approval from the Lands Conservation and
Reclamation Council (LCRC) prior to the development of a project
(Government of Alberta 2003). This Act was further amended in 1978 to
legally require operators to use conservation methods such as stripping
topsoil and storing it separately for later replacement. In 1993, the
Environmental Protection and Enhancement Act and the Conservation and
Reclamation Regulation were enacted to replace the Land Surface
Conservation and Reclamation Act. In addition, between 1978 and 1994 a
program was put in place to clean up sites on municipal and crown lands
that were disturbed and abandoned prior to formulating the legislation.
Similar reclamation acts were enacted in other provinces.
In Ontario, the Mining Act of 1990 is generally administered by the
Ontario Ministry of Northern Development and Mines and Part VII is
administered specifically by the "Director of Rehabilitation"
within that Ministry. The Act spells out the requirements for mine
closure and continual and sequential rehabilitation of mine sites or
mine hazards. Among the more notable provisions is subsection 4(1),
which generally requires that persons conducting mine rehabilitation
comply with the "Mine Rehabilitation Code of Ontario" which
includes schedules of the regulations and detailed performance standards
relating to the protection of public safety and the environment from
risks and hazards posed by various mine features (Wenig and
O'Reilly 2005).
British Columbia passed a regulation amending the Mines Regulation
Act in March 1969. This legislation was amended further in 1973 to
include coal and mineral exploration, sand and gravel pits and rock
quarries. The British Columbia Mines Act 1996, requires a mine owner,
agent or manager to file a plan outlining the details of the proposed
work and a program for conservation of cultural heritage resources and
protection of land, watercourses and cultural heritage resources
affected by mining (Government of British Columbia 1996).
The Saskatchewan Government introduced the first reclamation
requirement under the Mines Regulation Act in 1972. Prior to
this--during the 1930s and early 1970s--approximately 2,500 ha of land
near Estevan was mined by Prairie Coal Limited (Enzsol 1995).
"Unlike today, these properties were mined with no reclamation
guidelines in place," Enzsol (1995: 105) asserts. In 1984, the
early reclamation requirements, which were part of the permit approval
process for mining, were replaced by separate regulation when the
Saskatchewan Environment and Public Safety Department implemented the
Reclamation Guidelines for the Estevan Area (SERM 1996). This guideline
was applied between 1984 and 1992.
Regulations and Guidelines for Estevan
The two main items that have advanced ecological restoration
practices in the Estevan area since 1992 are the Mineral Industry
Environmental Protection Regulation 1996 (SERM 1996) and the
site-specific 1993 Guidelines for the sensitive terrains of Estevan. The
regulation states that the decommissioning and reclamation plan must
include a procedure, time frame and cost estimate for reclamation and a
proposal for the management and administration of the assurance fund.
The guideline specifies that the slope of regraded land intended for
agriculture should be less than 10% whereas that for end cuts intended
for wildlife habitat should be about 20%. In addition to this, 80% of
the surface area should be free of drainage water, in order to minimize
erosion (SERM 1993). In re-vegetating for agricultural use, good
agricultural practices should be followed and self-propagating species
of grasses, shrubs and trees should be selected for wildlife use.
Two critical issues arise from the regulations and guidelines for
decommissioning and reclamation in the Estevan area. First, mine
operators are expected to act according to the 'Precautionary
Principle', which stipulates that in the event of doubt about the
potential impacts of an action or operation, the company should avoid
taking a course of action that may jeopardize long-term viability of
species, ecosystems or the health of landowners, employees and local
residents. Second, effective evaluation of rehabilitation activities
must include scientific, regulatory and social perspectives.
Conventional scientific approaches (Marrs and Miao 2000) focus solely on
testing soil, water and vegetation parameters. However, studies by Irwin
(1995) and Baron et al. (1998) indicate that evaluating landscape change
requires an integration of social processes and natural sciences. Irwin
(1995: 2) juxtaposes the canons of official science with the canons of
citizen science to tell a convincing story about the emergence of a new
popular rationality. He argues for a criterion of proof based on
"the balance of probabilities" rather than the "beyond
all reasonable doubt" standard of state and corporate science. A
key component of the balance of probabilities is the incorporation of a
social context of judgement. Hence, gathering opinions of local people
broadens the scope of who are counted as 'experts' to include
beneficiaries of post-rehabilitation land use.
Methodological Approach
This paper assesses the impact of legislation and guidelines on
surface mine rehabilitation in the Estevan area of Saskatchewan, by
using a set of regulatory (Figure 2) and social criteria. These criteria
helped to assess the environmental performance of the mine operator
vis-a-vis the recommendations outlined in the 1993 Guidelines and the
1996 Regulations instituted by Saskatchewan Environment (SE). The social
criteria are based on local citizens' perceptions of the impact of
regulations on reclamation practices. Data were obtained from
reclamation reports, aerial photo interpretation and a survey, in 2001,
of three actors namely, SE regulators, officials of Luscar Ltd. (the
only mining company in Estevan) and local residents. Systematic
sampling, beginning with random numbers, was used to select 150
respondents from the Estevan area telephone directory. Two respondents
were chosen from the village of Roche Percee, 10 from Bienfait town, 12
from the Rural Municipality of Estevan and 126 from the city of Estevan
for a total of 150, in proportion to the 1996 population figures. Of the
150 respondents, 101 took part in the questionnaire-based interviews
while 49 participated in the focus group discussions.
Three officials of the mining company who are responsible for
reclamation were interviewed and three survey questionnaires were
distributed to SE officials of which 93% of the questions were answered.
Focus group discussions were used to obtain information on local
residents' perceptions of ecological rehabilitation practices in
the area. A group of 6 to 8 respondents was engaged in a discussion on
the quality and safety outcomes of rehabilitation in the Estevan area.
Although the approach for the interviews and focus group discussions
differed, they were complementary to each other.
Documentary sources of data and information included Environmental
Impact Statements (EIS), Semi-annual Reclamation Reports and SE Annual
Reports. The EIS of the Estevan area provided baseline information on
the biophysical characteristics of the pre-mining landscape, which is a
useful basis for measuring the progress of rehabilitation. The
reclamation reports detailed the total hectares of land mined and the
techniques employed for restoration. This paper examines large-scale
digital orthophoto maps (scale of 1:20,000) of the Bienfait, Boundary
Dam and Utility Mines which were produced by Orthoshop, Calgary,
Alberta, to show rehabilitated areas and areas of outstanding
rehabilitation. This approach was used by Herzog et al. (2001: 96) to
evaluate landscape destruction and rehabilitation in Saxony, Eastern
Germany.
[FIGURE 2 OMITTED]
Key indices for evaluating rehabilitation practices were adapted
from the 1996 Mineral Industry Environmental Protection Regulations and
the 1993 Guidelines (Figure 2). The description took into account (1)
the hectares for which various reclamation steps were taken; (2)
overburden and soil analysis programs and key results; (3) soil
amendments applied; (4) hectares of seeding and planting undertaken; (5)
results of germination/growth; (6) time frame for completing
reclamation; and (7) analysis of successes and failures. Descriptive
statistics were employed to depict spatio-temporal variation of the
hectares of land disturbed and rehabilitated between 1996 and 1999 at
the three mines.
Significant elements for social evaluation of ecological
restoration include quality and safety outcomes and the extent of
compliance with the regulations. Residents' perceptions concerning
the results of rehabilitation practices are rated from excellent (5) to
poor (1). Similar ratings for the safety outcomes of rehabilitation vary
from strongly agree (5) to strongly disagree (1). This social judgement,
as espoused by scholars such as Irwin (1995: 2) and Baron et al. (1998),
is important for assessing restoration practices. It is largely based on
local people's experiential knowledge of their immediate
environment.
Compliance or Non-compliance with Regulation
Luscar Ltd. is required by law to submit a pre-mining and
reclamation plan and a proposal for an assurance fund to SE to ensure
the decommissioning and reclamation of mining sites. Commenting on the
mine plan, an official of SE observed that Luscar Ltd. sets out its
reclamation plan in March of every year. Draft plans for mining and
restoration and the assurance fund which have been submitted by the
management of Luscar Ltd. since 1996, have met standards stipulated in
the 1996 regulations and have consequently been approved by the Minister
of Environment, Saskatchewan. An interview with SE regulators revealed
that the mining company has not defaulted in observing the requirements
of the assurance fund. The fund provides security against breach of the
permit conditions and rehabilitation requirements.
In order to monitor rehabilitation success, the mining company is
required to conduct field evaluations and submit semi-annual reclamation
reports to SE. The mining company submitted eight reclamation reports
between 1996 and 1999. The reports, supported by air photos, maps and
soil and plant surveys, illustrate hectares for which various
reclamation steps were undertaken, timing of all reclamation activities,
soil amendments applied and the results of seeding. These reports have
been reviewed and endorsed by SE officials.
Site-specific Restoration Programs
The issue of environmentally responsible mining in the Estevan area
is not whether the mine site will be restored, but the manner in which
restoration is accomplished. Luscar Ltd. is required to take measures in
dealing with and lessening the environmental impacts of coal mining
operations. An interview with officials of Luscar Ltd. revealed that
coversoil removal is normally conducted annually, during the unfrozen
conditions (summer), and takes place approximately six months ahead of
mining.
Currently, coal is mined by a 1,570W Bucyrus-Erie dragline, the
Prairie Queen, and 'Big Lou', a giant dragline (MacBean 2001:
4) in a series of parallel cuts--30 m wide strips up to 3.5 km in
length. Following coal removal, these pits are subsequently backfilled
and reclaimed in a regular manner: reclamation is done simultaneously
with mining operation. Overburden excavated from the active cut is used
to backfill the pit which is subsequently levelled. In line with the
rehabilitation plan, part of the spoil piles of mining has been levelled
to the required slope. Soil surveys undertaken by the mining company at
the Bienfait, Boundary Dam and Utility Mines indicate that topsoil
(A-horizon) materials with depths averaging 10-15 cm are found over the
pre-mined lands. The stockpiled soil is then spread on the levelled area
and seeded. A selective overburden handling technique' has been
incorporated into rehabilitation work at Bienfait, Utility and Boundary
Dam mines. According to mine officials, the technique selectively places
overburden materials with higher reclamation suitability into the upper
portion of the backfill of the mined lands (Luscar Ltd. 1996-2000).
Overburden materials (B-horizon) that are not suitable for plant growth
are buried deep in the backfilled area.
Site levelling and grading operations are undertaken by bulldozers,
scrapers and graders, with the objective of creating 10% slope and a
landscape acceptable to the proposed soft land uses: typically
agriculture (cropping), wildlife and recreation. Initial box cut and
final mine cuts normally retain greater slopes (10 to 20%). An
environmental planner of Luscar Ltd. indicated that after coversoiling,
the disturbed lands receive another lift in volume, which adds up to
approximately 15 cm in thickness after grading and compensates for the
metre of coal seam removed. According to the Guidelines, grading of land
should occur within two years of the initial disturbance (Luscar Ltd.
1996). Yet, soil replacement on parts of the mine sites of Bienfait,
Boundary Dam and Utility mines occurred within three years of initial
disturbance. In cases where cover soil was not available at a particular
site, engineers resorted to using other alternatives such as
transferring cover soil from other sites (Estevan Coal Corporation 1996)
instead of using suitable substrates such as residual hay, straw or wood
chip. Unless such 'supplier sites' have enough top-soil to
offset the deficiency, this practice can have adverse long-term
consequences such as nutrient depletion and low vegetative growth.
Revegetation of graded land for agriculture, rangeland and wildlife
is a significant part of ecological rehabilitation practices in the
Estevan area. Emphasis has been placed on quickly establishing
vegetation to control erosion and to achieve a self-sustaining plant
cover. Officials of Luscar Ltd. work in close collaboration with
personnel of SaskPower's Shand Greenhouse who currently conduct
revegetation in the Estevan area (SaskPower is the final custodian of
most of the rehabilitated lands in Estevan and owns the coalfields,
which are leased to the mining companies for mining operations). In
1999, germination trials were conducted at the greenhouse on five rare
native species for Luscar Ltd., including purple coneflower (Echinacea),
bird's foot trefoil (Lotus corniculatus), milkwort (Polygala
verticillata), salt bush (Baccharis halimifolia) and whorled milkweed
(Asclepias syriaca). These species have been used in seeding programs in
the Estevan area with 50% survival rates (Luscar Ltd. 2000).
In addition, measures were undertaken to prevent the transfer of
contaminated water into the underground water systems and Souris
River--the main river that drains the area. The SE-approved dewatering
procedure was followed. There was no water discharge from surface
impoundment and settling ponds at the Boundary Dam Mine between 1996 and
1997. However, between 1998 and 1999, a total of 899,208 m3 of water was
pumped from dewatering wells and settling ponds to approved discharge
points. Some of the water was discharged into SaskPower's Shand
Cooling Tower in 1999 (Luscar Ltd. 1999). Since this is a closed system,
there was no water quality analysis. Quality analysis was, however,
conducted on the remaining two-thirds of water discharged during the
period. Water samples were collected once a week and analyzed for
turbidity and suspended solids (TSS). The average TSS was 28.5 mg/l
which was below the legally allowed maximum level of 50mg/l (Table 1).
The average TSS for water tested at the Bienfait mine (total of
368,340.6 m3) between 1996 and 1999 was 19.8 mg/l which was below the
legally allowed maximum limit of 50 mg/l set by the SE guidelines
(Luscar Ltd. 1999). There was no water discharge from settling ponds in
1996, 1997, 1998 and 1999 (Luscar Ltd. 1996, 1999) at the Utility Mine
because settling ponds and wells were not in use.
A comparative study of the three sites revealed that a total of
734.81 ha were mined between 1996 and 1999 in the Estevan area. Out of
this figure, 444.03 ha have been successfully reclaimed and
decommissioned (Table 2). Thus, 60% of the total area disturbed has been
levelled to the acceptable slope of less than 10%. The proportion of
levelling is an improvement over the situation that existed before the
1993 Guidelines were developed when virtually nothing was done. However,
there was a shortfall in the rate of seeding. Only 17% of the total area
disturbed has been seeded which is equivalent to 29% of the total area
levelled. The problem is attributed to the harsh climate and soil
conditions of the area as well as equipment problems. Nevertheless,
portions of the three sites met SE's minimum standards and the
mining company has been released from further responsibilities of
restoration on these lands.
Overall, Boundary Dam Mine recorded the largest area mined between
1996 and 1999, accounting for 46% of the total area disturbed.
Similarly, the area rehabilitated was the highest of the three sites
studied. This was due to the commitment of more equipment and personnel
to rehabilitation activities during that period, as compared to the
other sites. Between two and five bulldozers were used in restoration
practices depending on the site-specific requirements of the area. An
equal number of personnel was also employed. The Utility Mine recorded
the second highest rate of disturbance after Boundary Dam Mine (Table
2). Out of the total area of 208.41 ha mined at the Utility Mine
(1996-1999), 136.97 ha have been successfully graded accounting for 31%
of total area levelled in the Estevan area.
Table 2 provides a comparison of the rates of disturbance, leveling
and seeding among the three mine sites. Bienfait Mine recorded the least
amount of area mined (189.13 ha) and restored during the period. The
area levelled at the Bienfait Mine accounted for 29% of the total area
levelled in the Estevan area. Aerial orthophoto map interpretation
confirmed the spatial-temporal variation in the rate of disturbance and
rehabilitation at the Boundary Dam, Utility and Bienfait Mines over the
years. About 60% of the levelled areas met SE's standards and were
released from reclamation obligations. SE inspectors consider the
overall rate of leveling as average.
Local Residents' Perceptions of Ecological Rehabilitation
Residents' perceptions of ecological rehabilitation practices
are based on knowledge of their immediate surroundings, their
observations of and encounters with the local environment through
cycling, hiking and hunting, among others. A portion of the residents
are either current or retired employees of the mining company and
demonstrated practical knowledge of mining and rehabilitation.
Residents' perceptions of ecological rehabilitation practices take
into consideration safety, soil, vegetation and water quality.
Out of the total number of 101 respondents, 28% rated ecological
rehabilitation as excellent and very good. "It looks better,
rolling and scenic, especially the area around Boundary Dam," a
resident commented. Some of the spoil piles have been levelled, grass is
flourishing and the land looks pretty much the same as what existed
before disturbance. A local farmer noted that before rehabilitation, it
was ugly and barren, and they have become accustomed to the piles for
many years. Residents cited lack of extensive woody vegetation cover as
a factor that impedes an ecologically diverse and aesthetically pleasing
landscape. The benefits of planting trees and shrubs are not often
realized until years after the legal responsibility for reclamation has
passed.
One-third of the respondents rated rehabilitation as average and
the same proportion viewed rehabilitation as either fair or poor (Table
3). Those who had lived in the Estevan area for a short period (1-10
years) rated the quality of rehabilitation work as poor or fair. This is
attributed to 'first impression syndrome'. A local resident
elaborated, "the nature of the spoils is an eye-sore, this is the
first thing visitors see when they come to Estevan." A retail store
manager stated categorically, "It is not happening fast enough.
There is not an equal digging/ reclaiming ratio." "Some of the
spoil piles have been levelled but still there is a lot to be
done," a retired miner explained. SE regulators concurred that a
serious breach of the 1996 Regulation for the Estevan area is that
restoration is approximately two years behind schedule and, if this
trend continues, the backlog of rehabilitation will increase.
Safety is very crucial to the success of reclamation. When
residents were asked to recount knowledge of cases of death or injury to
people who walk into rehabilitated areas, 85% asserted that they do not
know of any (Table 4). This category of resident participated in some
form of recreational activities in the area. Only 9% complained of a
threat to life and wildlife due to occasional depressions and gaseous
sinkholes. They reminisced about an incident where two children were
gassed to death at an old mine in the 1980s. This incident left an
indelible mark on this category of residents. However, officials of the
mine emphasized that areas which pose a threat to life have warning
signs and security fences to ward off trespassers. The remaining 6% of
the respondents had no idea whether the rehabilitated areas pose any
serious threat to life since they had not toured any of the areas to
verify.
Residents called for effective compliance monitoring on the part of
SE regulators. One local resident minced no words when he lamented,
"I am tired of over-regulation, enforce the regulations that are in
place." Residents are of the opinion that hefty fines or
restrictions on further mining until all outstanding rehabilitation is
completed will go a long way towards enforcing the regulations.
Residents suggested that in case of default on the part of the operator,
the province should hire a private agency to level the spoils and plant
trees, and the mining company should bear the cost of reclamation. In
view of this, residents suggested that a Resident Board or a Committee
be formed to bridge the gap between mine executives and locals so that
their views can be incorporated into reclamation programs.
Conclusion
This paper comments on a unique case of mine rehabilitation in
Estevan, Southern Saskatchewan, where there is only one mining company
and the reclamation guidelines are designed for the sensitive terrain
and site-specific conditions of the area. The reclamation and licensing
guidelines for Estevan provide detailed and systematic directions for
reclaiming the three mine sites of Boundary Dam, Bienfait and Utility to
a pre-determined land use objective. Site-specific evaluations of
rehabilitation work by SE officials give credence to the fact that about
60% of the disturbed area has been leveled and 17% seeded with a
seedling survival rate of 50%. Seeding has been difficult due to
equipment problems and the harsh physical conditions. This influences
the company's willingness and propensity to reclaim on a regular
and continuous basis. Generally, SE regulators and residents rated
reclamation work as average because it is not progressing fast enough.
In spite of the role of regulatory standards and guidelines for
land reclamation in the Estevan area, there is a need for more rigorous
research to be conducted into the soil properties in the area, to
ascertain the extent of the problem of saline soil, clayey soils and the
lack of organic matter. It must be emphasized that the science of mine
rehabilitation in the Estevan area should evolve from simple
revegetation activities to a discipline more reflective of ecologically
sustainable rehabilitation, which will ultimately involve long-term
management of the rehabilitated lands.
References
Alberta Environment. 1999. Focus On Land Reclamation. Alberta,
Canada: Queen's Printer.
Allen, E. B., S. J. Brown and M. F. Allen. 2000. Restoration of
Plant, Animal and Microbial Diversity. In Encyclopedia of Biodiversity,
vol. 5, S. Levin, ed.: 185-202. San Diego: Academic Press.
Baron, J. S., C. Bohlen, C. Gaudet, W. Jackson, B. Jones, J. R.
Karr, R. J. Naiman, B. Norton, M.M. Pollock and D. J. Rapport. 1998.
Evaluating landscape health: integrating societal goals and biophysical
process. Journal of Environmental Management 53:1-15.
City of Estevan. 2000. Estevan community profile. Estevan,
Saskatchewan.
Enzsol, T. 1995. An ecological land classification based land
management plan for old mined lands. In Ecological reclamation in Canada
at century's turn. Epp Henry, ed. Queen's Printer, Regina,
Saskatchewan.
Estevan Coal Corporation. 1996. Application for release from
further requirements for decommissioning and reclamation. Bienfait,
Saskatchewan.
Friedlander J. 2001. Design Principles for Reclamation of
Agricultural Lands. In Environmental Design for Reclaiming Surface Mines
B. Burley, ed. The Edwin Mellen Press, New York.
Government of Alberta. 2003. Environmental Protection and
Enhancement Act. Edmonton, Alberta, Canada: Queen's Printer.
http://www3.gov.ab.ca/env/ [Accessed on July 26, 2004].
Government of British Columbia. 1996. Mines Act. Victoria, BC:
Queen's Printer.
Haigh, M. 2002. Land reclamation and deep ecology: In search of a
more meaningful physical geography. Area 34(3): 242-252.
Harker, D., E. Sherri and K. Harker. 1993. Landscape restoration
handbook. Boca Raton, USA: Lewis Publications.
Herzog, F. A. Lausch, E. Muller, H. Thulke, U. Steinhardt and S.
Lehmann. 2001. Landscape matrics for assessing of landscape destruction
and rehabilitation. Environmental Management 27: 91-107.
Higgs, E. 2003. Nature by Design: People, Natural Process and
Ecological Restoration. Cambridge, Massachusetts: The MIT Press.
Irwin, A. 1995. Citizen science: A study of people, expertise and
sustainable development. Routledge Taylor & Francis Group, London.
Luscar Ltd. 1996-2000. Boundary Dam, Bienfait and Utility mines
semi annual-reports. Estevan, Saskatchewan.
MacBean, S. 2001. When Big Lou 'Walks' everything else
stops. Leader Post, Regina, August 3: 4.
Marrs, R. and Z. Miao. 2000. Ecological restoration and land
reclamation in open-cast mines in Shanxi Province. China Journal of
Environmental Management 59: 205-215.
Saskatchewan Environment and Resource Management (SERM). 1993.
Reclamation and licensing guidelines-Saskatchewan strip mined coal
lands. Regina, Saskatchewan: Queen's Printer.
Saskatchewan Environment and Resource Management (SERM). 1996. The
mineral industry environmental protection regulations. Regina,
Saskatchewan: Queen's Printer.
Skousen, J., P. Ziemkiewicz and C. Venable. 1998. Evaluation of
tree growth on surface mined lands in south west Virginia, Green Lands.
West Virginia University, USA: Extension Service.
Stokstad, P. 1998. Structuring a Reclamation Programme for
Abandoned Non-Coal Mines. Ecology Law Quarterly. 25: 121-165.
Wenig, M. and K. O'Reilly. 2005. The Mining Reclamation Regime
in the Northwest Territories: A comparison with selected Canadian and
U.S. jurisdictions. Proceedings of David Chambers Center for Science
January 21, 2005. University of Calgary, Canada.
RESEARCH NOTES include preliminary or summary descriptions of
research methods and/or results that do not yet address their full
theoretical, policy or practical implications. The intention is to
provide researchers and practitioners with a forum for presenting
interesting but preliminary ideas, methodologies, or results in the
spirit of fostering reflection and dialogue.
Abednego Aryee is a doctoral candidate in the University of
Waterloo--Wilfrid Laurier University Graduate Program in Geography. His
dissertation focuses on the impact of Environmental Information Systems
and Local Knowledge Systems on community-based agro-forestry management
and agro-diversity conservation. He also teaches university courses in
Geography part-time. He can be reached at arye0260@wlu.ca
Table 1. Boundary Dam and Bienfait Mine Water Discharges, 1996-1999
BOUNDARY DAM MINE BIENFAIT MINE
Total Volume Water Quality Total Volume Water Quality
of Water Analysis (SST) of Water Analysis (SST)
YEAR ([m.sup.3]) mg/l, mean values ([m.sup.3]) mg/l, mean values
1996 0 X 184,329.6 28.4
1997 0 X 0 X
1998 608,641 28.5 8,787 14
1999 290,567 X 175,224 17
Total 899,208 28.5 368,340.6 19.8
0 = No water was discharged from the mining area during the reporting
period
X = No water quality analysis
Estevan Coal Corporation 1997 and Luscar Ltd. 1998-2000
Table 2. Boundary Dam, Utility and Bienfait coal mine disturbance and
rehabilitation (levelling and seeding), 1996-1999
BOUNDARY DAM MINE UTILITY MINE
Area Area Area Area Area Area
Mined Levelled Seeded Mined Levelled Seeded
YEAR (ha) (ha) (ha) (ha) (ha) (ha)
1996 93.29 42.96 18.20 62.69 15.01 9.45
1997 110.95 104.58 23.36 33.5 22.7 5
1998 46.7 17.56 0.0 21.24 8.50 0
1999 86.33 13.01 0.0 90.98 90.76 28.34
Total 336.27 178.11 41.56 208.41 136.97 42.79
BIEN FAIT MINE
Area Area Area
Mined Levelled Seeded
YEAR (ha) (ha) (ha)
1996 36.51 20.98 25.33
1997 47.43 35.35 15.50
1998 43.55 40.68 2.20
1999 61.64 31.94 0.0
Total 189.13 128.95 43.03
Source: Luscar Ltd. Reclamation reports, 1996-1999.
Table 3. Responses to the question; how would you rate overall
rehabilitation work around Estevan?
Ratings Frequency Percentage
Excellent 6 6
Very Good 22 22
Average 37 36
Fair 18 18
Poor 18 18
Total 101 100
(Poor=1 Fair=2 Average=3 Very Good=4 Excellent=5)
Source: field survey, Estevan 2001.
Table 4. Responses to the question: do you think rehabilitated areas
have been made safe enough for human and wildlife access?
Ratings Frequency Percentage
Strongly Agree 8 8
Agree 68 67
Not Sure 15 15
Disagree 8 8
Strongly Agree 2 2
Total 101 100
(Poor=1 Fair=2 Average=3 Very Good=4 Excellent=5)
Source: field survey, Estevan, 2001.
COPYRIGHT 2006 Wilfrid Laurier
University Reproduced with permission of the copyright holder. Further reproduction or distribution is prohibited without permission.
Copyright 2006, Gale Group. All rights
reserved. Gale Group is a Thomson Corporation Company.
NOTE: All illustrations and photos have been removed from this article.